Sec. 31-259. - Schedule of charges.
(a) The following sewer connection fees are imposed:
Land Use | 2026 | 2027 | 2028 | 2029 | 2030 and Thereafter
Residential, single-family and duplex uses, (cents per total square foot) | 69.2 | 75.1 | 81.6 | 88.6 | 96.2
Mobile homes used as a residence (for each mobile home pad) | $2,311 | $2,510 | $2,726 | $2,960 | $3,215
All other residential uses (for each individual family unit) | $2,341 | $2,543 | $2,761 | $2,999 | $3,257
Commercial and industrial and institutional uses (for each acre) | $16,300 | $17,702 | $19,224 | $20,877 | $22,673
The rates shown in the "2026" column shall be charged beginning on the effective date hereof, until and including December 31, 2026.
The rates in each column thereafter will apply between January 1 and December 31 of the respective years, except that the rates shown in the "2030 and Thereafter" column will remain in effect until such time as the fees are amended by the city council. The date to be used for the calculation of sewer connection fees will be the date of initial application for building permit.
(b) For the "Residential, single-family and duplex uses" land use in the above table, the fee shall be calculated by multiplying the rate in the table (in cents) by the total square footage of the permit, to include garage, shed, basement (finished and unfished), and above grade house areas.
(c) The commercial and industrial and institutional charge shall be computed to the nearest 1/100 acre (but excluding outlots and floodway), but the fee shall in no event be less than the applicable fee for a single-family unit in subsection (a)(1) above. As used herein, the expression "institutional" refers primarily to religious assembly facilities and public and private schools. The connection fees for such institutional uses will be computed on acreage including the developed land, parking areas, and the land immediately adjacent to the facility which forms the usable part of the property, excluding unsewered playgrounds or sports activity areas. Commercial and industrial acreage shall be based upon the entire commercial or industrial zoned area, including any parking and outside storage areas.
(d) If, in the opinion of the superintendent of the permits and inspections division, with the advice of the city engineer, a commercial or industrial connection is likely to significantly exceed the rate of flow of the peaking factor of two times 1,500 gallons per acre per day, a surcharge shall be computed on the basis of the Carollo study, and transmitted to the city council for approval by resolution. Following such approval, the commercial or industrial connection shall be charged the fee set out above, plus the surcharge.
(e) The fees provided for in this division are in addition to all other sewer connection or use fees provided for elsewhere in this Code.
(Code 1980, § 31-259; Ord. No. 32118, § 1, 7-17-90; Ord. No. 33137, § 1, 12-21-93; Ord. No. 35417, § 1, 12-19-00; Ord. No. 36982, § 1, 3-29-05; Ord. No. 38436, § 1, 6-9-09; Ord. No. 40444, § 2, 8-18-15; Ord. No. 42866, § 1, 2-8-22; Ord. No. 44760, § 1, 8-4-26)