Report of work—Approval.
Tulsa Revised Ordinances tit. 11-C, § 508
in effectSection 508. - Report of work—Approval.
Any person doing any sanitary sewer work must notify the Director as soon as the pipe work has been completed and is ready for inspection, and must keep the trench open and the pipe fully exposed for inspection until the inspection is completed. If such work is approved, a certificate of satisfactory inspection shall be issued to the contractor.
Source: City of Tulsa, Revised Ordinances and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/ok/tulsa/codes/code_of_ordinances?nodeId=COOR_TIT11-CWASE_CH5REUSSASESY_S508REWOPPFetched: 10/28/2026