§ 11-35-6 — REVIEW AND APPROVAL PROCEDURES

Mesa City Code (Supp. No. 22: codified through Ordinance No. 5996, adopted March 9, 2026) · Mesa City Code § 11-35-6

Corpus is an independent public-information project, not the official City of Mesa website. Stable reference: corpuslaw.us/code/4b90781c-2a84-4f0b-857a-40333bf708a3

11-35-6: - REVIEW AND APPROVAL PROCEDURES

A. The following wireless communication facilities are permitted by right with a Zoning Certificate issued under the provisions of Chapter 68, Zoning Clearance, if they comply with all applicable requirements of Section 11-35-5. All other facilities that are not exempt from regulation require approval of a Special Use Permit by the Zoning Administrator or Board of Adjustment, pursuant to Chapter 70, Conditional Use Permits and this Section: 1. The following facilities when located on a property in non-residential use in any Commercial or Industrial District: a. Any microcell facility. b. Any antenna that is mounted on any existing building or other structure when the overall height of the antenna and its supporting Tower, pole or mast does not exceed the maximum height of zoning district in which it is located, or when attached to existing Street light, or utility poles. c. Any camouflaged facility designed and built to appear as an architectural element of an existing building, or as an architectural structure designed to be consistent with the approved design theme for the development site, provided: i. All materials and design elements used in the camouflaged design are compatible with the approved materials, colors and design of the buildings and structures used for the development site; ii. The overall height of the camouflaged facility is no higher than twice the maximum height permitted for the zoning district; iii. The facility is a minimum distance of twice the proposed height of the facility from a Residential Zoning District. 2. The following facilities when located on a property in non-residential use in any Industrial District: a. Any free standing Antenna Structure and its supporting Tower, pole, or mast that complies with all applicable setback ordinances, provided: i. The overall height of the antenna and its supporting structure does not exceed a height of 70-feet; and ii. The location of the facility is a minimum of 300-feet from a residence. b. Freestanding Stealth facilities provided the overall height of the facility (not including stealth related masking features for Antennas and antenna mounts) and its supporting structure does not exceed and height of 70- feet. 3. The following facilities when located on a property in any zoning district: a. Any building mounted facility, including roof mounts and wall mounts, provided any additional height required for the facility is less than 15- feet above the height of the existing building. b. Any co-located facilities mounted on existing freestanding poles or Towers, provided: i. Any additional height required for the facility is less than 15-feet above the initial approved height of the pole or Tower; ii. The existing number of communication providers with facilities on the pole does not exceed 3. Co-location of a fourth provider shall require approval of a Special Use Permit. 4. Undergrounding Required. All wires and/or cables necessary for operation of an antenna shall be placed underground or attached flush with the surface of the building or the structure of the antenna. B. All requests for Special Use Permit, height exceptions, or Zoning Clearance review shall follow the procedures set forth in Article 7, Administration, and the following requirements: 1. Any application that proposes construction of a new Antenna Structure or alternative Tower structure or placement of a new antenna on an existing structure of any type shall require a pre-application meeting with Planning Division staff. This meeting is intended to provide significant preliminary information on the project, discuss development alternatives, and determine the appropriate review procedure. 2. Any application that proposes construction of a new Antenna Structure or alternative Tower structure or involves the placement of any type of communications equipment on or within an architectural form that requires an exception to a height limit shall require review by the Planning & Zoning Board. C. The Zoning Administrator may approve the following modifications to existing structures provided the modification is consistent with the requirements of this Chapter and any applicable conditions of approval of a Special Use Permit. 1. The use of a single Tower by multiple carriers unless conditions of the Special Use Permit specify otherwise. 2. An increase in the height of an existing antenna support structures that does not exceed 10 feet, provided, the increase in height is used to facilitate the co- location of another communications provider on the same structure and does not exceed the maximum height set forth in other applicable City requirements for a Tower on that site. 3. An application for building-mounted equipment provided the request is consistent with the requirements of this Chapter and other applicable City requirements and will not increase the height of an existing structure by more than 15 feet. D. Approval of a Special Use Permit by the Zoning Administrator acting as a Hearing Officer or Board of Adjustment is required for the following: 1. Any proposal for a new, freestanding communications facility or to increase the height of an existing antenna support structure greater than 15-feet in any agricultural or residential district; 2. Any application for a building or roof-mounted structure that would exceed the height of the existing structure by more than 15 feet, except applications as listed in Paragraph A, above; and 3. Any application that proposes an exception to any applicable requirement in Section 11-35-5. E. In addition to any other findings that this Ordinance requires, in order to approve any Special Use Permit for a facility subject to regulation by this Chapter, the decision-making authority must find, based on substantial information in the record including, where required, technical analysis by an approved radio frequency engineers, calculations by a State-licensed structural engineer, or other evidence that: 1. The proposed telecommunication facility will comply with all applicable state and federal standards and requirements; 2. The proposed project is consistent with the general requirements of this Chapter and any specific requirements applicable to the proposed facility; 3. The proposed antenna or related facility, operating alone and in conjunction with other telecommunications facilities, will comply with all applicable state and federal standards and requirements; and either: a. Will not be readily visible; or b. Will be readily visible, but it is not feasible to incorporate additional measures that would make the facility not readily visible. 4. The facility, if it is not a microcell or co-located, is necessary to prevent or fill a significant gap in coverage or capacity shortfall in the applicant's service area, and is the least intrusive feasible means of doing so; 5. If the proposed facility is a satellite dish or parabolic antenna exceeding 39 inches in diameter, that a smaller or less intrusive antenna cannot feasibly accomplish the provider's technical objectives and that the facility will not be readily visible; 6. If a new antenna support structure is proposed or the applicant proposes to extend the height of an existing Tower, that the applicant has made good faith and reasonable efforts to locate a telecommunication facility on a support structure other than a new monopole or lattice Tower or to accomplish co-location and that no existing Tower or structure in the vicinity can accommodate the applicant's proposed antenna; 7. If a modification of height, separation, setback, Landscaping or other requirements of Section 11-35-5 is proposed, that the proposed modification is consistent with the purposes of this Chapter and will be the least intrusive feasible means of meeting the service provider's objectives; 8. If the proposed location is in a Residential district that the location is necessary for the provision of personal wireless services to Mesa residents and businesses, or their owners, customers, guests, or invitees, or other persons traveling in or about the City based on substantial evidence that siting the facility outside of a Residential district is infeasible and without the proposed facility, the operator will be unable to provide personal wireless services to its customers in the proposed coverage area, or unable to provide the capacity necessary to meet call volumes 9. If the proposed location is readily visible from the habitable area of a dwelling unit within 300 feet or from a public Right-Of-Way, public park, or other public recreation or cultural facility, that: a. It is not feasible to provide the service at another location or to incorporate additional measures such as a decrease in height, increase in the number of number of facilities, increase in setback, change in design, relocation relative to other structures or natural features, that would further reduce its visibility; and b. The proposed telecommunication facility provides an important link in applicant's service area build-out and is necessary to meet its service needs to City residents. F. The Zoning Administrator Hearing Officer or Board of Adjustment may waive or modify requirements of this Chapter upon advice of the City Attorney that denial of the application would have the effect of prohibiting the provision of telecommunications services, unreasonably discriminating among service providers, or constituting any other violation of State or Federal Law. The applicant shall have the burden of proving that the denial or requirement for compliance would violate applicable Federal or State Law.

Ask a question about Mesa law

Corpus searches the Mesa sections it holds and shows the ones that match, with their citations. Free, no sign-in.