Compliance schedules.
Reno Administrative Code § 12.16.760
in effectSec. 12.16.760. - Compliance schedules.
Should any schedule of compliance be established in accordance with the requirements of this article, the following conditions shall apply to such schedule:
(a) The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the industrial user to meet the applicable categorical pretreatment standards (e.g., hiring an engineer, completing preliminary plans, completing final plans, executing contract for major components, commencing construction, completing construction, etc.);
(b) No increment referred to above shall exceed nine months;
(c) Not later than 14 days following each date in the schedule and the final date for compliance, the industrial user shall submit a progress report to the city including, at a minimum, whether or not it complied with the increment of progress to be met on such date and, if not, the date on which it expects to comply with this increment of progress, the reason for delay, and the steps being taken by the industrial user to return the construction to the schedule established. In no event shall more than nine months elapse between such progress reports to the city.
(Ord. No. 6305, § 1, 8-28-13)
Source: City of Reno, Nevada, Administrative Code, City Charter and Annexation and Land Development Code (Municode Library, library.municode.com)URL: https://library.municode.com/nv/reno/codes/administrative_code?nodeId=PT2READCO_TIT12PUWOUT_CH12.16SESE_ARTIIIREWADI_DIV4RENORE_S12.16.760COSCFetched: 11/1/2026