Approval of tariff mechanisms for automatic annual adjustment of charges for jurisdictional costs of new or modified transmission facilities.
SDCL § 49-34A-25.1
in effect49-34A-25.1. Approval of tariff mechanisms for automatic annual adjustment of charges for jurisdictional costs of new or modified transmission facilities.
Notwithstanding any other provision of this chapter, the commission may approve a tariff mechanism for the automatic annual adjustment of charges for the jurisdictional costs of new or modified transmission facilities with a design capacity of thirty-four and one-half kilovolts or more and which are more than five miles in length. For the purposes of §§49-34A-25.1 to 49-34A-25.4, inclusive, electric transmission facilities and electric transmission lines covered by this section include associated facilities such as substations and transformers.
SL 2006, ch 239, § 1.
Source: South Dakota Legislature (sdlegislature.gov)URL: https://sdlegislature.gov/Statutes/49-34A-25.1Fetched: 10/20/2026