Who conducts the project closeout?
25 C.F.R. § 170.474
in effectThe following table shows who must conduct the TTP construction project closeout and develop the report.
If the project was
completed by . . .
then . . .
and the closeout report must . . .
(a) BIAThe region engineer or designee is responsible for closing out the project and preparing the report(1) Summarize the construction project records to ensure compliance requirements have been met;
(2) Review the bid item quantities and expenditures to ensure reasonable conformance with the PS&E and modifications;
(3) Be completed within 120 calendar days of the date of acceptance of the TTP construction project; and
(4) Be provided to the affected Tribes and the Secretaries.
(b) A TribeAgreements negotiated under ISDEAA, or other appropriate agreements specify who is responsible for closeout and preparing the report(1) Meet the requirements of ISDEAA;
(2) Comply with 25 CFR 900.130(d) and 131(b)(10) and 25 CFR 1000.249, or the Program Agreement, as applicable;
(3) Be completed within 120 calendar days of the date of acceptance of the project; and
(4) Be provided to all parties specified in the agreements.