Utility foreman certificate; presence of certified utility manager or certified utility foreman required.
O.C.G.A. § 43-14-12
in effect43-14-12. Utility foreman certificate; presence of certified utility manager or certified utility foreman required.
(a) As used in this Code section, the term 'division' means the Division of Utility Contractors.
(b) No person shall be employed as a utility foreman unless such person holds a valid current utility foreman certificate issued by the division.
(c) The division shall certify all applicants for certification under this Code section who satisfy the requirements of this Code section.
(d) No utility system shall be constructed, erected, altered, or repaired unless a certified utility manager or certified utility foreman who holds a current certification is present at the job site of such construction, erection, alteration, or repair of the utility system.
(e) Any individual seeking certification as a utility foreman under the provisions of this chapter shall file an application with the division on a form prescribed by the division, pay the required fees established by the State Construction Industry Licensing Board, and meet the following requirements:
(1) Successfully pass a board approved examination with a minimum score of 70;
(2) Have completed at least one year of full-time experience in the field performing the construction, erection, alteration, or repair of utility systems under the supervision of a licensed Utility Manager;
(3) Submit proof of completion of 12 hours of board approved safety training courses, which shall include eight hours of Competent Person Training for Excavations and four hours of Competent Person Training for Confined Spaces; and
(4) Provide a signed affidavit by a current or former employer attesting to the completion of experiential requirements. Each employer who oversaw the completion of projects which satisfied the experiential requirements shall provide their own signed affidavit. Qualifying experience under this subsection shall be obtained through a combination of roles, including, but not limited to, crew member, lead worker, assistant foreman, utility operations, construction support, or other field based positions, provided the work was performed under the required supervision, and shall include:
(A) Assisting with review of construction plans, utility maps, and job specifications, identifying underground and overhead utilities, coordinating activities with project managers, engineers, inspectors, and utility representatives, verifying permits, locates, and clearances, and assisting with planning crew assignments, equipment needs, and work schedules;
(B) Participating in daily job safety analyses and safety meetings, performing work in compliance with Occupational Safety and Health Administration standards and applicable local, state, and federal regulations, including traffic control requirements, working in properly protected trenches, participating in confined space entry activities, using required personal protective equipment, and reporting incidents, near misses, and hazards;
(C) Assisting with supervision of utility crews, monitoring safe operation of equipment, supporting productivity tracking and daily work coordination, and assisting with resolution of routine onsite issues;
(D) Assisting with coordination of material delivery and staging, inspecting materials and equipment for damage or irregularities and reporting findings, and participating in the proper use and routine maintenance of heavy equipment;
(E) Participating in the installation of water, sewer, gas, electrical, and telecommunications utility systems installed on a fee-for-service basis, including bedding, backfill, compaction, and erosion and sediment control measures, in accordance with project specifications and utility standards;
(F) Inspecting work for compliance with plans and specifications under supervision, assisting with daily logs, production reports, as-built documentation, and documenting utility locations and field changes; and
(G) Communicating job site conditions, safety concerns, and work progress to a supervising Utility Foreman or Utility Manager.
(f) An application for a certification under this Code section shall constitute express consent and authorization for the Secretary of State or his or her representative to perform a criminal background check. Each applicant who submits an application to the Secretary of State for certification agrees to provide the Secretary of State with any and all information necessary to run a criminal background check, including, but not limited to, classifiable sets of fingerprints. The applicant shall be responsible for all fees associated with the performance of such background check.
(g) An applicant may request an oral administration of the examination.
(h) The decision of the division regarding the qualifications of licensure shall, in the absence of fraud, be conclusive.
(i) Any person or entity violating this Code section shall be subject to discipline and penalties as provided in this chapter, including, but not limited to, license denial, suspension, revocation, administrative fines, injunction, or any other lawful enforcement action authorized by the division.