Sec. 25-8. - Construction and building debris.
(a) Scope. The provisions of this section shall apply to all persons, contractors or subcontractors performing any hauling, excavation, alteration, demolition, construction or reconstruction or work related or incidental thereto on any site within the city and to any person, contractor or subcontractor making use of any public street, alley or way owned or maintained by the city as a result of such activity.
(b) Depositing on public streets. No person shall deposit, track or scatter any dirt, stone, gravel, brick, cement, concrete, sand, mud, wood, trash, garbage, rubbish or other similar material or debris upon any public street, alley or other public way.
(c) Vehicles leaving construction sites. No person, contractor or subcontractor performing all or part of the work described in subsection (a) of this section shall allow any vehicle to leave such job site and enter or travel upon a public street, alley or way unless such vehicle is properly covered and all equipment of the vehicle, including the tires thereof, are properly cleaned so as to prevent a violation of subsection (b) of this section.
(d) Abatement of violation.
(1) Should any person, contractor or subcontractor performing all or part of the work described in subsection (a) of this section violate the provisions of subsection (b) or (c) of this section, the city may issue an order, in writing, to any person, contractor or subcontractor on the job site where such violation originated to cease specified activity on such site relating to the violation of this section, including but not limited to hauling, excavation, construction, demolition or reconstruction at the job site or removal of any material from the job site.
(2) No person, contractor or subcontractor issued an order as specified in this subsection shall continue or cause or allow the activity covered by the order to continue after the issuance of the order until written permission to resume the activity covered by the order has been given. No written permission to resume the activity covered by the order shall be given until the city, in its sole discretion, is satisfied that all steps necessary to prevent future violations of this section have been taken.
(e) Removal; costs of removal by city.
(1) Should any person, contractor or subcontractor violate subsection (b) of this section, the person, contractor or subcontractor responsible for such violation shall remove such litter from the public street, alley or other public way within two (2) hours of notification by the city of the violation.
(2) If any person, contractor or subcontractor responsible for such violation shall fail to timely abate the violation after notification to do so, the city may remove or arrange to have removed the litter, and the costs of such removal, along with an administrative fee in an amount established by the city council and on file in the office of the city secretary, shall be charged to the person, contractor or subcontractor responsible for the violation.
(3) If the person, contractor or subcontractor responsible for such violation shall fail to pay such costs within twenty-four (24) hours of written notice of the costs incurred, the city may issue an order, in accordance with subsection (c) of this section, requiring the person, contractor or subcontractor to cease work at such job site until all costs are paid.
(f) Appeal of order; assessment. Any person who is aggrieved by an order or assessment made pursuant to this section may appeal, in writing, such order or assessment within ten (10) days of the notification of the order or assessment to the city manager. The city manager, within ten (10) days of the filing of the appeal, shall hold a hearing to consider the validity of the action appealed from and render a decision thereon.
(Code 1966, § 21-14)