§ 23-87 — Wastewater discharge permits
Charlotte City Code (Supp. No. 57: codified through Ordinance No. 10171, enacted June 22, 2026) · Charlotte City Code § 23-87
Corpus is an independent public-information project, not the official City of Charlotte website. Stable reference: corpuslaw.us/code/53d25d8a-c48a-406a-becc-393f6a029187
Sec. 23-87. - Wastewater discharge permits.
(a) Application. Application for a wastewater discharge permit shall be in accordance with the following: (1) All connections and discharges made to the POTW are subject to approval by CMUD. Any user proposing to discharge any industrial waste to the POTW or who is doing so must make application to CMUD for a wastewater discharge permit. (2) Any industrial user proposing to change the volume or characteristics of an existing discharge shall request from CMUD a determination as to whether or not a new application should be filed and shall provide sufficient information on the proposed change to enable CMUD to determine the need for a new application. If the proposed change requires a revision in a current SIU or local permit or requires a different type of permit be issued, the IU shall apply to CMUD for an appropriate wastewater discharge permit within 45 days of the notification. (3) When requested by CMUD, a user must deliver to CMUD information on the volume and characteristics of its wastewater, to include, but not to be limited to, self-monitoring of the indirect discharge, within 30 days of the request. CMUD is authorized to prepare forms for this purpose and may periodically require users to update this information. (4) Any person discharging or proposing to discharge wastewater into the POTW shall be responsible at all times for determining the volume and characteristics of its existing or proposed discharge. (b) Requirements. Wastewater discharge permit requirements are as follows: (1) No person meeting one or more of the requirements of an SIU of this article shall discharge wastewater into the POTW without first obtaining a wastewater discharge permit from CMUD. An SIU that has filed a timely application pursuant to subsection (c) of this section may continue to discharge pending final action on the application so long as its indirect discharge is in compliance with subsections 23-79(a) through (d). CMUD may require the user to demonstrate compliance by performing monthly or more frequent monitoring of the indirect discharge and analyzing for the POTW's pollutants of concern and applicable categorical pretreatment standards. (2) CMUD may require other users to obtain wastewater discharge permits as necessary to carry out the purposes of this article. (3) Any violation of the terms and/or conditions of a wastewater discharge permit shall be deemed a violation of this article. Obtaining a wastewater discharge permit does not relieve a permittee of the continuing obligation to comply with all federal and state pretreatment standards and/or requirements or with any other requirements of federal, state and local law. (c) Contents of application. Each industrial user required to apply for a permit shall complete and file with CMUD an application, in the form prescribed by CMUD, which may include, but not be limited to, the following: (1) Name, mailing address and location. (2) SIC numbers for the IU's primary, as well as all secondary, functions and processes. (3) Analytical data on wastewater constituents and characteristics, including, but not limited to, those mentioned in subsection 23-79(e) of this article, any of the priority pollutants (Section 307(a) of the Act) which the applicant knows or suspects are present in the discharge as determined by a laboratory certified by the state to perform the analysis associated with the determination, and any other pollutant of concern to the POTW. Sampling and analysis shall be performed in accordance with procedures approved by the Environmental Protection Agency and CMUD and as required in subsections 23-91(1) and (m). (4) Time and duration of the indirect discharges. (5) Average daily and 30-minute peak wastewater flow rates, including daily, monthly and seasonal variations, if any. (6) Site plans, floor plans, mechanical and plumbing plans and details to show all sewers, floor drains, sewer connections, direction of flow and appurtenances by the size, location and elevation. (7) Description of activities, facilities and processes on the premises, including all materials which are or could be accidentally or intentionally discharged. (8) Where known, the nature and concentration of any pollutants in the discharge which are limited by any pretreatment standards in effect and a statement as to whether or not the pretreatment standards are being met on a consistent basis and, if not, whether additional operation and maintenance and/or pretreatment is required for the user to meet applicable pretreatment standards. (9) If additional operation and maintenance and/or pretreatment will be required to meet the pretreatment standards, the shortest schedule by which the IU will provide such additional pretreatment. The completion date in this schedule shall not be longer than the compliance date established for the applicable pretreatment standard. The following conditions apply to this schedule: a. The schedule shall contain progress increments in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the IU to meet the applicable pretreatment standards. No increment in the schedule shall exceed nine months, and no schedule of compliance shall exceed a total of 24 months. b. No later than 14 days following each date in the schedule and the final date for compliance, the IU shall submit a progress report to CMUD including, at a minimum, whether or not it complied with the increment of progress, the reason for the delay, and, if appropriate, the steps being taken by the IU to return to the established schedule. In no event shall more than nine months elapse between such progress reports to CMUD. (10) Each product produced by type, amount, process and rate of production. (11) Type and amount of raw materials processed (average and maximum per day). (12) Number and type of employees, hours of operation of the plant and proposed, or actual, hours of operation of the pretreatment system. (13) If subject to a categorical pretreatment standard, a baseline monitoring report in accordance with 40 CFR 403.12(b) and 15A NCAC 2H .0908(a), as outlined in subsection 23-91(a). (14) Any other information as may be deemed by CMUD to be necessary to evaluate the permit application. (15) Description of current and projected waste reduction activities in accordance's with G.S. 143-215.1(g); (d) Application signatories and certification. All wastewater discharge permit applications and user reports must be signed by the current authorized representative of the user on file with the control authority as defined in section 23-77 and contain the following certification statement: "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to ensure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief, true, accurate and complete. I am an authorized representative of the user and am authorized to execute this certification on behalf of the user. I am aware that there are significant penalties for submitting false information in violation of this certification, including the possibility of fines and/or imprisonment." (e) Application review and evaluation. CMUD is authorized to accept, review and evaluate applications for wastewater discharge permits to the POTW. CMUD may conduct an inspection of the facility to verify information contained in the permit application. Within a reasonable time following receipt of the application, CMUD shall either accept the application as complete or return the application to the applicant as incomplete with a statement of what additional information is required. After all required information has been received by CMUD, a determination shall be made as to whether or not a wastewater discharge permit will be issued. CMUD may deny any incomplete application for a wastewater discharge permit if the applicant fails to submit all required information within the time specified by CMUD.
(Ord. No. 5230, § 1(Exh. A), 10-28-2013)
Ask a question about Charlotte law
Corpus searches the Charlotte sections it holds and shows the ones that match, with their citations. Free, no sign-in.