19.12.060 - Preliminary geologic and/or soil report.
A. When Required. When the tentative map is filed, the director, on the advice of the city engineer, shall determine whether a preliminary geologic and/or soil report is required. If, due to previous investigation or knowledge of the geologic conditions and soil qualities of the subdivision and adjacent territory, the director, on the advice of the city engineer, determines that no geologic hazards are present, no geologic and/or soil report will be required for the tentative map. If in the same manner, the director, on the advice of the city engineer, determines that uncorrectable geologic hazards are present, the tentative map shall be disapproved. If neither of the foregoing determinations can be made, the director shall require that a preliminary geologic and/or soil report be filed.
B. Preparation. The preliminary report shall be prepared by a civil engineer or engineering geologist who is registered by the state of California, specializing in the field of soil and geologic analysis. Geologic investigation shall be performed under the supervision of an engineering geologist registered and certified by the state, except that geologic investigation, not for the purpose of determining engineering data, may be supervised by a geologist registered by the state. Soil investigation shall be performed under the supervision of a civil engineer registered by the state specializing in the field of soil analysis.
C. Basis. The preliminary report shall be based on a field geologic and/or soil investigation of the proposed subdivision and such surrounding territory as may in the opinion of the director be necessary, and on an analysis of the design of the proposed subdivision and of the proposed and existing structures within said subdivision and such surrounding territory. Geologic and soil information shall be based on adequate test borings, excavations, earth tests, and/or such other investigations, analyses and sources of information as are necessary, in the opinion of the director, on the advice of the city engineer, to determine the presence or absence of geologic hazards.
D. Contents. The preliminary report shall determine the existence, potential existence or likelihood of any geologic hazards. If geologic hazards are found within or adjacent to the proposed subdivision, or may affect such subdivision, proposed or existing structures, or adjacent territory, such hazards shall be considered in the report. The said report shall include a geologic map which shall show the boundaries of the areas in which such hazards exist, and the report shall recommend corrective measures to mitigate such hazards. If critical geologic hazards exist on or adjacent to the proposed subdivision, the said report and the tentative map for which the report is submitted shall list, lot by lot, every lot within the proposed subdivision which the critical geologic hazards are likely to affect, if not corrected.
E. Action. The director shall act upon the preliminary report required within 30 days after such report is filed with him, and shall inform the subdivider of the results of such action.
F. Hazards Not Identified-Hazards Inadequately Investigated-Corrective Measures Inadequate. If the director, on the advice of the city engineer, finds that, contrary to the preliminary report, geologic hazards do exist, or that such geologic hazards exist and have not been adequately investigated, analyzed or located, or that recommended corrective measures may not mitigate such geologic hazards, he shall disapprove the tentative map and require the subdivider to file a new tentative map and geologic and/or soil report.
G. Uncorrectable Hazards. If the director, on the advice of the city engineer, determines that no corrective action will mitigate such geologic hazards, he shall disapprove the tentative map.
H. Approval. The director, on the advice of the city engineer, shall not approve any tentative map for a proposed subdivision for which a preliminary report has been required unless such report has been filed and unless he is satisfied that all geologic hazards have been adequately identified and analyzed, and that adequate corrective measures have been recommended where indicated. If he is so satisfied, he shall approve the tentative map, subject to the condition that, where geologic hazards have been identified, the subdivider shall take whatever action the director, on the advice of the city engineer, deems necessary to mitigate such hazards, and subject to the further condition that if, before the final map is recorded the director, on the advice of the city engineer, finds that geologic hazards not previously identified do exist, or that geologic hazards have not been adequately identified, analyzed or located, or that corrective measures may be inadequate or that uncorrectable geologic hazards exist, approval of the tentative map shall be deemed to have lapsed.
I. Use. When a preliminary geologic and/or soil report has been prepared, that fact shall be noted on the tentative map. Five copies of the said geologic and/or soil report shall be submitted to the director for review by the city and any other companies, officers, department, jurisdictions, agencies or bodies to which copies of the tentative map are sent for consideration pursuant to Section 19.12.090 and Section 19.12.120 of this chapter.
(Prior code § 9210.)