33.848.070 Impact Mitigation Plan Requirements
The applicant must submit an impact mitigation plan which includes all the components listed in this
Section. The review body may modify the proposal. While it is important to include adequate detail
in the plan, the intent of this Chapter and the IR zone is to allow development of a document that
guides the nature and timing of mitigation activity rather than one that specifies the nature, size,
and location of all future development projects.
A.
Mission statement and uses. An impact mitigation plan must include a mission statement.
The mission statement is intended to identify the scope of services and defines the range of
uses and activities that the institution sees as ultimately occurring within the campus. The
mission statement must include the following elements:
1.
A statement of the mission of the institution and the campus;
2.
A list of all the primary uses expected to occur on the campus with an explanation of
the interrelationship between each and the institutional campus mission;
3.
A list of all accessory uses expected to occur on the campus with an explanation of the
role each accessory activity plays in implementing the campus mission statement.
Except for Small Scale Energy Production, activities which provide goods or services to
people or facilities that are not on the campus may not be listed as
accessory activities;
4.
A list of temporary activities and events which are expected to occur on the campus in
general and at major event entertainment facilities located on the campus;
5.
A list of other retail sales and service, office and industrial activities expected on the
campus providing goods or services to people or facilities in the larger community,
with a statement for each explaining the interrelationship between the activity and
the campus mission statement; and
6.
The proposed locations for retail sales and service, office, industrial uses, and major
event entertainment facilities must be identified.
B.
Institutional campus boundary. The Impact Mitigation Plan must delineate the ultimate
area and boundaries of the institution’s campus. The proposed boundary may include land
that the institution does not presently control. However, sites must be controlled by the
institution to be zoned IR.
C.
Location sensitive uses. The Impact Mitigation Plan must identify the location on the
campus where location sensitive uses are to be placed. Location sensitive uses are:
1.
Retail Sales And Service and Office uses which are not listed as primary or accessory
uses in the mission statement;
2.
Any use or activity which provides goods or services to establishments not on
the campus;
3.
Major Event Entertainment facilities permitted on the campus as conditional
uses; and
4.
Industrial Service and Manufacturing And Production uses permitted on the campus
as conditional uses.
D.
Phasing of mitigation activities. Impact mitigation measures and expected demands for
public services should be divided into phases of campus growth. Each phase of campus
growth included in the impact mitigation plan must identify the specific mitigation activities
which will be implemented in advance of the development activities included in that
growth phase. A specific phase of campus growth may include several different
development projects. Phases of growth may be described exclusively in terms of the
mitigation measures to be implemented. Once the implementation measures for a phase of
growth are in place any development project which is otherwise consistent with the
campus mission statement and the impact mitigation plan may be undertaken when the
project's expected impacts are at or below the levels mitigated for in the current phase of
growth. Each phase of growth must identify mitigation measures to be taken to address the
elements in Subsections E through I of this Section.
E.
Waste disposal. For each phase of campus development, the following service loading
must be addressed:
1.
Effect on the City's sanitary sewer system;
2.
Capacity of the storm water disposal system that serves the campus;
3.
Disposal of hazardous solid waste, including preventing hazardous substances from
entering the storm water disposal and sanitary sewer systems; and
4.
Preventing mud and other debris from campus construction sites from entering the
storm water disposal system.
5.
Reducing solid waste produced on the campus through recycling;
F.
Water supply. For each phase of campus development the following service loading must
be addressed:
1.
Water needs of the campus; and
2.
Water conservation activities and measures.
G.
Transportation. For each phase of campus development the following must be addressed
in the multi-modal transportation plan.
1.
The location and amount of motor vehicle and bicycle parking;
2.
Strategies to reduce the number of motor vehicle miles traveled by those traveling to
and from the campus, i.e. students, patients, faculty, staff, and visitors, including:
a.
Measures to encourage those traveling to and from the campus to use
alternatives to single-occupant auto trips (walking, bicycling, carpooling, and
public transit);
b.
The car or van pool programs;
c.
Incentives to be offered to employees and, where applicable, students, and
others to use public transit for travel to and from the campus;
d.
Incentives to be offered to employees and, where applicable, students, and
others to travel on foot or by bicycle to and from the campus. This may include
incentives for employees to live within walking distance of the campus;
3.
Planned improvements to the routes used by transit patrons between transit stops
serving the campus and the campus’s circulation system for pedestrians and
transit facilities;
4.
An on-site circulation system for all modes that meets the City’s connectivity
standards of no more than 530 feet apart for streets and no more than 330 feet apart
for pedestrian/bicycle connections where streets are not feasible, and links to
adjacent streets and walkways;
5.
Traffic impacts on the streets in the vicinity of the campus and measures which will be
taken to ensure that the surrounding streets will function consistent with the
Transportation Element of the Comprehensive Plan;
6.
Parking mitigation, including an analysis of projected peak parking demand for daily
activities and events, and strategies to reduce the supply of parking without impacting
nearby land uses; and
7.
To address adequacy of transportation services, a multi-modal impact study is
required of the applicant by the Bureau of Transportation. In preparing such a study
the applicant should follow the guidelines set forth in the “Transportation Impact
Study Guidelines” document available from the Portland Bureau of Transportation.
H.
Environmental, historic, scenic and open space. For each phase of campus development
the following must be addressed:
1.
A strategy for the protection and enhancement of environmental, scenic and historic
resources which have been inventoried by the City, determined to be significant and
are located within the land occupied by the campus; and
2.
A strategy for the enhancement of the campus's system of open spaces and their
linkage to public right-of-ways.
I.
Neighborhood livability. For each phase of campus development the following must
be addressed:
1.
Steps that will be taken to mitigate adverse impacts on the livability of nearby
residential neighborhoods and residential developments as well as non-institutionally
owned properties within the institution campus boundary. Impacts include noise,
odor, traffic, litter, parking, shading of adjacent areas, public safety, vibration
and glare;
2.
How the institution's development will accommodate continued provision of public
services including transportation, police, and fire protection to locations which are
within the campus boundary but are not under the institution's control;
3.
A schedule for bringing the campus into compliance with all provisions of the zoning
code which may be practicably met as well as any conditions attached to the
establishment or expansion of the institutional campus or the approval of the campus
impact mitigation plan;
4.
A plan showing how the campus will comply with the regulations for superblock if the
campus is subject to the superblock regulations. If the institution’s site includes more
than 50,000 square feet of vacated rights-of-way the institutional campus must meet
the development regulations for superblocks contained in Chapter 33.293; and
5.
Identification of distinct service or amenities the institution will provide for
nearby residents.
J.
Neighborhood communication and coordination. The institutional campus must provide
an ongoing process for communicating with neighbors. The process is to be implemented
during all phases of growth provided for by the impact mitigation plan. This process must
provide for the following:
1.
The institution must host a meeting, at least annually, with representatives from
recognized neighborhood and business associations within whose boundaries the
institution is located. The purpose of the meeting is to discuss short term and long-
range plans for campus building and development.
2.
A process for meeting with representatives of recognized neighborhood and business
associations within whose boundaries the institution is located, which provides for the
following:
a.
The periodic review of the institution's services and activities and potential
external impacts;
b.
An opportunity to review and comment upon the design of specific development
proposals planned in the current or next growth phase; and
c.
An opportunity to be informed of all land use reviews the institution is applying
for at least 30 days before they apply to the City. The institution must provide
information on the types of activities, proposed size, and proposed location
along with any proposed mitigation plan measures.
K.
Design compatibility. The impact mitigation plan must include guidelines or standards that
will guide the design review process on the campus. The guidelines or standards must
include the following elements:
1.
A set of design review guidelines and procedural thresholds to mitigate the potential
aesthetic impacts of large scale institutional development upon surrounding non-
institutional development and public right-of-ways. For each specific development
project located near the campus boundaries or abutting a right-of-way, the applicant
must demonstrate compliance with these design guidelines prior to the granting of a
building permit. This will be processed through a Type II or a Type Ix design review
procedure at the completion of schematic design. A Type II procedure must be
followed if the impact mitigation plan's design guidelines take the form of subjective
or qualitative statements. The institution may choose a Type Ix procedure if the design
guidelines are objective standards;
2.
Each building facade within 50 feet of a public right-of-way or pedestrian path or
recreational trail (as shown in the Portland Comprehensive Plan Transportation
Element) within or bordering the institutional campus must comply with design
guidelines which address the following:
a.
All developments must create an environment friendly to pedestrians
through the:
(1) Orientation of main entrances to facilitate visibility and accessibility to
pedestrians and transit patrons;
(2) Treatment of ground floor development;
(3) Provision of pedestrian amenities including seating, informational and
directional signs and lighting; and
(4) Treatment of open spaces and other landscaped areas.
b.
All development located, in all or part, within 150 feet of a campus boundary
abutting a residential or commercial/mixed use zone must also be designed to
smooth the transition between more intense, larger-scale institutional
development and nearby residential and commercial areas through the:
(1) Treatment of campus gateways including their location, design
and landscaping;
(2) Building design including proportions; building massing; type and color of
exterior building materials; window treatment including number, size,
location and degree of transparency; building setbacks and landscaping; and
masking of roof-mounted mechanical equipment, loading docks and trash
collection areas; and
(3) Design, landscaping and location of surface and structured parking.
3.
A listing of any specific building design characteristics for which a blanket adjustment
to zoning regulations is requested for current and future building projects must be
included in the institution's design guidelines.