18.70.070 - Required information on construction documents.

A. General. The construction documents shall show all necessary dimensions and materials for plan review and construction and shall accurately reflect the results of the engineering investigation and design. B. Existing construction. The construction documents shall show the existing diaphragm and shear wall sheathing and framing materials, fastener type and spacing, diaphragm and shear wall connections, continuity ties, and collector elements. The plans shall also show the portion of the existing materials that needs verification during construction. C. New construction. 1. Foundation plan elements. The foundation plan shall include the size, type, location and spacing of all anchor bolts with the required depth of embedment, edge and end distance; the location and size of all columns for braced or moment frames; referenced details for the connection of braced or moment frames to their footing; and referenced sections for any grade beams and footings. 2. Framing plan elements. The framing plan shall include the width, location and material of shear walls; the width, location and material of frames; references on details for the column-to-beam connectors, beam-to-wall connections, and shear transfers at floor and roof diaphragms; and the required nailing and length for wall top plate splices. 3. Shear wall schedule, notes and details. Shear walls shall have a referenced schedule on the construction documents that includes the correct shear wall capacity in pounds per foot; the required fastener type, length, gauge and head size; and a complete specification for the sheathing material and its thickness. The schedule shall also show the required location of three-inch (3") nominal or two (2) two-inch (2") nominal edge members; the spacing of shear transfer elements, such as framing anchors or added sill plate nails; the required hold down with its bolt, screw or nail sizes; and the dimensions, lumber grade and species of the attached framing member. Notes shall show required edge distance for fasteners on structural wood panels and framing members; required flush nailing at the plywood surface; limits of mechanical penetrations; and the sill plate material assumed in the design. The limits of mechanical penetrations shall also be detailed showing the maximum notching and drilled hole sizes. 4. General notes. General notes shall show the requirements for material testing, special inspection, structural observation and the proper installation of newly added materials. 5. Registered design professional of record's statement. The responsible registered design professional of record shall provide the following statements on the approved construction documents: a. "I am responsible for designing this building's seismic strengthening in compliance with the minimum seismic resistance standards of Chapter 18.70 of the Long Beach Municipal Code." and when applicable: b. "The Registered Special Inspector, required as a condition of the use of structural design stresses requiring continuous inspection, will be responsible to me."

(ORD-25-0019 § 1(Exh. A), 2025; ORD-22-0033 § 1(Exh. A), 2022; ORD-19-0031 § 1(Exh. A), 2019; ORD-16-0026 § 1(Exh. A), 2016)