Rights-of-way permits.
Tulsa Revised Ordinances tit. 49, § 906
in effectSection 906. - Rights-of-way permits.
A. Rights-of-way minor construction permit. When a rights-of-way minor construction permit is required pursuant to Title 35, Tulsa Revised Ordinances, Chapter 4, an application fee of Two Hundred Forty-Two Dollars ($242.00) shall be charged in addition all other applicable permit fees as identified in Title 11, Chapter 12. Contractors for this work must have an annual contract with the City of Tulsa in accordance with Title 35. This section shall not apply to "Rights-of-Way Occupants," and their contractors as defined in Title 11, Chapter 12.
B. Sidewalk and driveway permit fee. The location of the proposed work shall determine the fees and bonds and the proposed work shall be defined and established by referencing the adopted and currently effective Tulsa Metropolitan Area Major Street and Highway Plan.
1. Non-arterial sidewalk and driveway permit. Any person applying for a residential use permit to construct or repair any sidewalk, driveway, or curb in the City of Tulsa Non-Arterial Rights-of-Way shall be required to provide a good and sufficient bond or insurance, or a combination of both, in favor of the City of Tulsa in the sum of not less than Five Thousand Dollars ($5,000.00). Contractors applying for commercial use permits to construct or repair any sidewalk, driveway, or curb in the City of Tulsa Non-Arterial Rights-of-Way shall reference Title 35, Chapter 2 for bonding, insurance, and annual contract requirements. The permit fee for this work shall be Two Hundred Forty-Two Dollars ($242.00).
2. Arterial sidewalk and driveway permit. Contractors constructing or repairing any sidewalk, driveway, or curb in the City of Tulsa Arterial Rights-of-Way shall reference Title 35, Chapter 2 for bonding, insurance, and annual contract requirements.
C. Right-of-way temporary use of street fees. The location of the proposed work shall determine the fees and insurance and the proposed work shall be defined and established by referencing the adopted and currently effective Tulsa Metropolitan Area Major Street and Highway Plan.
1. Non-arterial temporary use of streets. Any person applying for a permit to temporarily use the City's non-arterial rights-of-way shall pay the City of Tulsa a permit fee equal to Two Hundred Forty-Two Dollars ($242.00). Inspection fee based on Title 49, Section 108. Temporary use of street permits will be issued according to Title 35, Section 500. It does not include the construction described in paragraph 906.A. above.
2. Arterial temporary use of streets. Contractors requesting temporary use of street permits in the City of Tulsa Arterial Rights-of-Way shall reference Title 35, Chapter 2 for insurance requirements. If the placement is in an arterial street, fees required by Title 11, Chapter 12 will apply.
(Ord. No. 24664, § 1, 8-25-2021; Ord. No. 25351, § 1, 7-17-2024)
Source: City of Tulsa, Revised Ordinances and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/ok/tulsa/codes/code_of_ordinances?nodeId=COOR_TIT49ADPELIFE_CH9INDEPEFE_S906RI-WPEFetched: 10/28/2026