in effect12.2.502: MINIMUM CLEARANCE FROM OVERHEAD LINES:
A. For the purposes of this section, the term "Clearance" shall mean the shortest distance between any two (2) surfaces.
B. Minimum clearance between any building or other structure and any overhead transmission line, overhead distribution facility, or electric pole shall be maintained in accord with the provisions of the National Electrical Safety Code, as adopted by the Regional Building Code. Clearance exceeding those specified by the National Electrical Safety Code may be required by Utilities in circumstances, including, but not limited to, meeting Utilities design criteria and providing for changes in future use of the surrounding facilities or Utilities' facilities.
C. Minimum clearance between trees, bushes, foliage, signs, chimneys, radio and television antennas, tanks and other installations not classified as buildings or structures, and any overhead transmission line, overhead distribution facility or electric pole shall be maintained in accord with the provisions of the National Electrical Safety Code, as adopted in the Regional Building Code 1 .
D. Minimum clearance over streets, alleys, parking lots, rights- of-way and easements by any overhead transmission line or overhead distribution facility shall be maintained in accord with provisions of the National Electrical Safety Code as adopted by the Regional Building Code.
E. Any person who proposes any action that would result in violation of the minimum clearances as set out in subsections B and C of this section shall give ninety (90) days' prior notice of the proposed action to Utilities. Any person who proposes to change the use of land or change the grade of land that would result in conflict with subsection D of this section shall give ninety (90) days' prior notice of the action. Upon notice, Utilities shall determine the feasibility of relocating the line, distribution facility and/or electric pole which is in conflict with the proposed action to a suitable and safe location. Should it be determined by Utilities that relocation is feasible, Utilities shall perform the necessary relocation at the expense of the person whose proposed action violates the minimum clearance requirement. Relocation of the overhead transmission line, distribution facility and/or electric pole shall begin on the date as Utilities may designate.
F. Should it be determined by Utilities that the relocation of a transmission line, distribution facility and/or electric pole is not feasible, Utilities may require other action as will prevent a violation of the minimum clearance requirement. Any action which Utilities may require pursuant to this subsection shall be performed at the expense of the person whose proposed action violates the minimum clearance requirement.
G. In the event that the required ninety (90) day notice is not received by Utilities, the City or Utilities shall not be liable for any damage or injury to persons or property caused by or resulting from failure to maintain the minimum clearance prescribed by this section. The person whose action violates the minimum clearance requirement or property owner on whose property the violation exists shall be deemed to have assumed the risk of any resulting damage or injury and to have impliedly agreed to indemnify the City and Utilities against the loss, which indemnity shall run with and be a charge upon the land upon which the clearance requirement is violated.
H. When Utilities has reasonable cause to believe that there may exist on any premises a minimum line clearance violation, the Chief Executive Officer may enter upon any premises at any reasonable hour for the purpose of inspecting, abating, removing or preventing any condition.
I. In the event that the owner or occupant of any premises located within the City refuses to permit entry by the Chief Executive Officer when entry is sought pursuant to subsection H of this section, the Chief Executive Officer may make application to any Judge of the Municipal Court of the City for the issuance of an inspection warrant. The application shall identify the premises upon which entry is sought and the purpose for which entry is desired, and shall state the facts giving rise to the belief that a minimum line clearance violation exists at the premises. Any warrant issued pursuant to the application shall command the owner or occupant to permit entry by the Chief Executive Officer for the purpose stated therein. (Ord. 98-173; Ord. 01-42; Ord. 18-42)
Notes
1 | 1. The Building Codes are adopted by Council in chapter 7 of this Code, the City's Zoning Code.
Source: City of Colorado Springs, Colorado, City Code and City Charter (American Legal Publishing, codelibrary.amlegal.com)URL: https://codelibrary.amlegal.com/codes/coloradospringsco/latest/coloradosprings_co/0-0-0-19620Fetched: 11/1/2026