27.28.270 - Response to statement of claims.
A. Public Works Contracts will require the City to respond, in writing, to a Statement of Claims by indicating whether:
1. A Claim, in whole or in part, is disputed and the basis of any such dispute; or
2. The Contractor provided insufficient information to determine the validity of the Claims.
B. The Public Works Contract will require the City to pay the Contractor the amount of any Claims, or portions of Claims, not in dispute.
(Ord. 30540.)