Sec. 36-97. - Performance guarantee.
In those instances where a project is essentially complete, with the exception of some individual elements of the approved development plan that cannot be completed due to unusual and unique circumstances, and that otherwise prevent the occupancy of the land and/or building, the administrative official may allow the deposit by the applicant with the city in the form of cash, certified check, or irrevocable letter of credit drawn on a bank located within the city, an amount sufficient to insure performance of the applicant to make those remaining improvements, whether public or private, at a later date as provided for herein. The option of providing a performance guarantee shall be solely at the discretion of the administrative official. In no case, however, shall the option of providing a performance guarantee be made available to delay the completion of any improvement directly relating to the public health or safety.
(1) Generally. The performance guarantee shall:
a. Be prepared on forms approved by the city attorney and submitted in completed form to the planning and building department for approval by the administrative official.
b. Insure or guarantee the construction and completion of the remaining improvements, as set forth in the approved development plan over a period not to exceed six months.
c. Be in an amount equivalent to 100 percent of the estimated cost of completion of the remaining improvements (both public and private). Such estimate shall be prepared by the applicant and submitted to the city engineer for review and approval. The applicant's submission shall consist of either an engineer's estimate of cost, or the actual contracted cost of the work. In both instances, the cost shall be itemized and shall include the unit costs used to determine the final cost. It shall be at the discretion of the city engineer to accept the validity of the applicant's submittal, or adjust it as necessary to achieve a more realistic cost figure.
d. Provide for the release of all of the monies so obligated, upon the demand of the city, without further condition or requirement for legal action, in accordance with the requirements of this article.
(2) Type. Performance guarantees securing the construction of the proposed improvements shall be secured to the city by one of the following methods or combination thereof:
a. Cash, deposited with the city clerk, or deposited in a local bank in an account assigned to the city.
b. Cashier's check deposited with the city clerk.
c. Certificates of deposit assigned to the city.
d. An irrevocable letter of credit from a local bank, and assigned to the city.
e. An escrow account set up in a local bank, such funds to be held in a special account and only distributed by the bank with the approval of the city, and subject to audit by the city.
The city expressly reserves the right to reject, at the discretion of the administrative official, any guarantee it considers to be inadequately secured. The submitted performance guarantee shall not be in the form of a surety bond.
(3) Term. The term of the performance guarantee, whether cash, a cashier's check, an irrevocable letter of credit, or escrow account shall extend a minimum of three months longer than the approved construction period required for installation of the subject improvements.
(4) Issued by whom.
a. Extent. The performance guarantee submitted shall insure or guarantee, to the extent specified by the city engineer in his estimate of cost, the construction and completion of all remaining improvements, both public and private, proposed by the approved development plan.
b. Business interests. In no event shall the company or bank securing the performance guarantee have any material or other property interest in the proposed project to which the performance guarantee relates, nor have any other business relationship with the applicant in any other development or project that would, from the standpoint of the city, be considered a conflict of interest. The company or bank shall attach to the performance guarantee a notarized disclosure statement fully disclosing all current and impending business relationships with the applicant.
c. Eligibility.
1. To be eligible, all companies and banks shall be approved by the city attorney.
2. Banks must be licensed under the laws of the United States or the State of Mississippi, and located and operating within the city.
d. Performance. If the company or bank fails to comply with any of the provisions of the performance guarantee, or fails to release the obligated monies to the city upon demand, they shall not be allowed to act in that capacity for any project within the jurisdiction of the city for a period of five years, and shall be subject to the penalties herein established. The city attorney shall take such other actions in law or equity as may be required to secure all obligated funds.
(5) Release of guarantee.
a. Inspection. Prior to termination of the applicant's obligation to the city, all of the required improvements shall be constructed under the observation and inspection of the applicable inspecting agency, and shall be either accepted for maintenance, in the instance of public improvements, or given final approval by the administrative official, in the instance of private improvements.
b. Release of performance guarantee, procedure.
1. The applicant may, from time to time, request partial release of the obligated sum contained in the performance guarantee as work progresses. Such a request shall be in writing, addressed to the administrative official, and shall specify the work that has been completed as well as the work that remains to be completed. The amount requested for release shall be determined by using current market values for materials and labor, and shall not exceed the ratio of work completed to the entire amount of improvements secured.
2. Upon receipt of such request, the administrative official shall direct the applicable inspecting agencies to verify the actual level of completion and prepare a report on the requested release for presentation to the administrative official. The report may recommend release of the amount requested, or recommend some other amount which, based upon their investigation, more accurately reflects the actual level of completion in relation to the entire amount of improvements secured.
3. Upon receipt of the reports from the applicable inspecting agencies, the administrative official may take action on the applicant's request. The administrative official may approve the applicant's request, approve the amount recommended by the various inspecting agencies, approve the release of some other amount which the administrative official feels more accurately reflects the actual level of completion, or deny the request. In no instance shall the administrative official approve an amount greater than the amount requested by the applicant.
4. Following action on the requested release, the administrative official shall notify, in writing, the surety holding the performance guarantee authorizing the specific release. Until such time as the administrative official shall, by such written authorization addressed to the surety, release the specified amount, the surety shall continue to hold the obligated sum as established in the agreement.
5. In no case shall more than 90 percent of the total performance guarantee be released over the term of the guarantee. The final ten percent of the performance guarantee shall only be released after the administrative official certifies that all improvements have been completed in their entirety, constructed in accordance with the approved development plan, and meet all of the city's required standards and specifications.
c. Failure to complete. If, at the end of the performance period, all of the improvements secured by the performance guarantee have not been completed, the administrative official shall:
1. Require the surety to perform on the guarantee and pay to the city such amount as shall be required to complete the improvements; or,
2. Require the applicant to submit a new performance guarantee for a period not to exceed six additional months, and which has been recalculated in order to allow for inflation as a result of the extended period.
(Ord. of 8-3-99(1), § 1.14)