§ 17.64.070 — Release of improvement security
Victorville, California, Municipal Code (Supp. No. 57: codified through Ordinance No. 2466, passed April 7, 2026) · Victorville Municipal Code § 17.64.070
Corpus is an independent public-information project, not the official City of Victorville website. Stable reference: corpuslaw.us/code/630ca80d-4295-4a7a-b050-86d9e796c8a2
17.64.070 - Release of improvement security.
The improvement security required under Section 17.64.060 of this chapter, shall be released in the following manner: (1) Security for faithful performance of any act or agreement shall be released upon the final completion and acceptance of the act or work subject to the provisions of subsection (2) of this section; (2) The city council may release a portion of the security in conjunction with the acceptance of the performance of the act or work as it progresses upon application therefor by the subdivider; provided, however, that no such release shall be for an amount less than thirty percent of the total improvement security given for faithful performance of the act or work and that the security shall not be reduced to an amount less than thirty percent of the total improvement security given for faithful performance until final completion and acceptance of the act or work. In no event shall the city council authorize a release of the improvement security which would reduce such security to an amount below that required to guarantee the completion of the act or work or any other obligation imposed by this title, the Subdivision Map Act or the improvement agreement; (3) Security given to secure payment to the contractor, his subcontractors and to persons furnishing labor, materials or equipment shall, six months after completion and acceptance of the act or work, be reduced to an amount equal to the amount of all claims therefor filed and of which notice has been given to the city's finance department plus an amount reasonably determined by the city council to be required to insure the performance of any other obligations secured thereby. The balance of the security shall be released upon the settlement of all such claims and obligations for which the security was given; (4) No security given for the guarantee or warranty of work shall be released until the expiration of the guarantee or warranty period. Upon the failure of the subdivider to complete the improvement acts or obligations within the time specified, the city council may, upon notice in writing of not less than ten days, served upon the person responsible for the performance thereof, or upon notice in writing of not less than twenty days served by registered mail, addressed to the last known address of such person, determine that the subdivider is in default and may cause the improvement security or such portion thereof as is necessary to complete the work or act, and any other obligation of the subdivider secured thereby, to be forwarded to the city.
(Ord. 999 § 1 (part), 1985)
Ask a question about Victorville law
Corpus searches the Victorville sections it holds and shows the ones that match, with their citations. Free, no sign-in.