Springfield, Ill., City Code § 154.25 Notice of violation.
§ 154.25. - Notice of violation.
(a) The office of public works, department of building and zoning, shall issue a notice of violation if the erosion control plan is not being implemented or the conditions of the permit are not being met. The notice of violation shall state the violation, the corrective action necessary and the day by which the correction must be completed.
(b) If the corrective action specified in a notice of violation is not completed in the specified time period, a stop work order may be issued. The office of public works, department of building and zoning, shall determine the extent of the order, which may include all work at the site except for the corrective action.
(c) If no reasonable effort at a corrective action is made, or if immediate corrective action is necessary, the office of public works, department of building and zoning, may cause the corrective action to be performed and shall assess the actual and administrative costs of such performance against the permittee.
(d) A stop work order may be issued at any time if work is being done without a valid, current permit, or contrary to this Code.
(e) A failure to obtain applicable permit(s) for a land disturbance or land development activity, or a failure to comply with the requirements of the erosion control permit or the provisions of this chapter, shall be deemed a violation.
(Ord. No. 105-3-12, § 1(Exh. A), 3-6-12)