§ 30-3-24 - ALIGNMENT.
(A) The single office shall determine the alignment of reserved right-of-way during:
(1) the review and approval process for a development application; or
(2) if an applicant files a waiver request under Section 30-3-41 (Waiver Request), not later than the 60th day after the waiver request is filed.
(B) The alignment of reserved right-of-way is based on:
(1) the alignment established in the transportation plan, collector plan, or capital improvement project; and
(2) engineering criteria, including grade, curvature, and the existence of a flood plain.
(C) In an area designated for a state roadway project, alignment may be established by the Texas Department of Transportation.
(D) For an existing or platted street, the alignment is based on:
(1) the existing centerline established before an additional dedication from the opposite side of the right-of way occurs; or
(2) if the centerline of the street is proposed to be shifted from its present alignment, the proposed centerline.
(E) If the alignment for a roadway cannot be determined under Subsection (D), the reserved right-of-way shall be established equally on each side of the centerline of the existing roadway.
Source: City Code Section 25-6-54; County Code Section 82.202(f)(3) and (4); Ord. 031211-11; Ord. 031211-42.