§ 19.18.020 — Standards for and timing of traffic impact analysis

El Paso City Code (Supp. No. 95, Update 4: codified through Ordinance No. 019889, enacted June 23, 2026) · El Paso City Code § 19.18.020

Corpus is an independent public-information project, not the official City of El Paso website. Stable reference: corpuslaw.us/code/64f406c2-0894-4c2e-be23-d18576d7ccba

19.18.020 - Standards for and timing of traffic impact analysis.

A. TIA and Update Required. A TIA shall be submitted with a zoning application, a preliminary plat or with the land study. If previously submitted, an updated TIA shall also be submitted with the final plat if substantial changes have been made from the preliminary plat, and shall be generally consistent with the TIA submitted with the preliminary plat. The initial TIA may also be updated whenever the plan for the proposed development is modified to authorize more intensive development. B. Contents. 1. The TIA on a land study (or preliminary plat or zoning application if no land study is provided) shall identify or determine the following: a. Trips to be generated by the proposed development trip generation shall be calculated using the latest edition of ITE's Trip Generation Manual or trip generation rates approved by the City of El Paso; b. Distribution and assignment of such trips to the road network analyzed; c. The capacity of affected thoroughfares before and after the proposed development. Capacity shall be quantified by level-of-service based on the latest version of the Highway Capacity Manual. The volume to capacity ratio (v/c) shall be included in the level-of-service tables. The capacity analysis shall include the AM and PM peak hours, twenty-four-hour, and special times or days of the week dependant of the land use's peak traffic generating time periods as determined from the latest version of ITE's Trip Generation Manual. Additional factors such as pedestrian trips, bicycles, and mass transit as possibly mitigating vehicle trip counts shall be considered where warranted; d. Deficient thoroughfares or roadways shall be determined based upon the minimum acceptable level-of-service as put forth in the following table: Table 19.18-1. Required Minimum Acceptable Level-of-Service (Roadways) Level-of-Service Without Proposed Development Proposed Developed Projected Level-of-Service | A | B | C | D | E | F A | A | - | - | - | - | - B | B | B | - | - | - | - C | B | C | C | - | - | - D | B | C | C | A D | - | - E | B | C | C | A D | AB E | - F | B | C | C | A D | AB E | AB F A The city may choose to participate in roadway improvements to restore a minimum level-of-service C. B In cases where the level-of-service of the roadway network without development is below a level-of-service D the proposed development shall not increase roadway intersection delay. The city manager or designee may deem that the proposed development cannot be supported by the existing roadway network. e. The development project's proportionate share of the costs of such thoroughfares and modifications including rights-of-way. 2. The TIA on a preliminary plat and a zoning application (or building permit if not submitted previously, or final plat if no preliminary is provided) shall identify or determine the following: a. Turning movements at intersections, access points and median breaks; b. Analysis of median breaks, ingress and egress and all intersections, including a queue analysis, for both AM and PM peak hours and special times or days of the week dependant of the land use's peak traffic generating time periods as determined from the latest version of ITE's Trip Generation Manual; c. The capacity of affected intersections before and after the proposed development shall be reported, based on the latest version of the Highway Capacity Manual, adjusted to reflect existing signal timing plans. The volume to capacity ratio (v/c) shall be included in the intersection level-of-service tables; d. Deficient intersections and capacity. Deficient intersections shall be determined based upon the minimum acceptable level-of-service as put forth in the following table: Table 19.18-2. Required Minimum Acceptable Level-of-Service (Intersections) Level-of-Service Without Proposed Development Proposed Developed Projected Level-of-Service | A | B | C | D | E | F A | A | - | - | - | - | - B | B | B | - | - | - | - C | B | C | C | - | - | - D | B | C | C | A D | - | - E | B | C | C | A D | AB E | - F | B | C | C | A D | AB E | AB F A The city may choose to participate in roadway improvements to restore a minimum level-of-service C. B In cases where the level-of-service of the roadway network without development is below a level-of-service D the proposed development shall not increase roadway intersection delay. The city manager or designee may deem that the proposed development cannot be supported by the existing roadway network. e. Specific recommendations for thoroughfare, intersection, and roadway improvements and traffic control modifications and other traffic improvements to mitigate the traffic from the proposed development (any proposed signal timing must include the entire coordinated system not just intersections within the TIA study area); f. The development project's proportionate share of the costs of such improvements and modifications including rights-of-way; and g. Specific recommendations including but not limited to bus turnouts, auxiliary lanes, traffic calming, location of access points, location of median cuts, parking lot layout and site distance. 3. The method of preparing the TIA shall be as approved by the city traffic engineer. C. Capital Improvements Plan For Roads. The capacity of a thoroughfare may be considered adequate for purposes of a TIA if a needed improvement is included, funded, and approved in the city's, county's or state's two-year capital improvements plan for roads, or, if the improvement is included, funded, and approved in the city's, county's or state's three- to five-year capital improvements plan for roads, provided that the applicant agrees to phase development to conform to such scheduled improvement. This chapter shall not be construed to prevent the city from requiring dedication of rights-of-way for such roads, or from assigning trips to such roads in a TIA in order to determine a development project's proportionate costs of improvements. D. Use Intensity Table. Where a proposed plat application does not designate the land use or intensity of use proposed for the development, for purposes of ascertaining the applicability of this chapter and the trips to be generated, the city may utilize typical uses and intensities of use. For land to be developed for nonresidential or multiple-family use in the city's extraterritorial jurisdiction, the city may utilize uses and intensities of use that are typical in the most intensive zoning district that authorizes the type of use proposed in the development.

(Ord. 16882 § 2 (part), 2008) (Ord. No. 17739, § 2, 3-6-2012)