§ 152.68 — Review and approval of a floodplain development permit application

Code of Ordinances, City of Dayton, Ohio (Supp. No. 36: codified through Ordinance No. 32173-25, passed December 31, 2025) · Dayton City Code § 152.68

Corpus is an independent public-information project, not the official City of Dayton website. Stable reference: corpuslaw.us/code/672e39e1-b44a-4bb4-97c5-b9efd7aaadcb

Sec. 152.68. - Review and approval of a floodplain development permit application.

(A) Review. (1) After receipt of a complete application, the Floodplain Administrator shall review the application to ensure that the standards of these regulations have been met. No floodplain development permit application shall be reviewed until all information required in Section 152.67 has been received by the Floodplain Administrator. (2) The Floodplain Administrator shall review all floodplain development permit applications to assure that all necessary permits have been received from those federal, state or local governmental agencies from which prior approval is required. The applicant shall be responsible for obtaining such permits as required including permits issued by the U.S. Army Corps of Engineers under Section 10 of the Rivers and Harbors Act and Section 404 of the Clean Water Act, and the Ohio Environmental Protection Agency under Section 401 of the Clean Water Act. (B) Approval. Within 30 days after the receipt of a complete application, the Floodplain Administrator shall either approve or disapprove the application. If the Floodplain Administrator is satisfied that the development proposed in the floodplain development application conforms to the requirements of this chapter, the Floodplain Administrator shall issue the permit. All floodplain development permits shall be conditional upon the commencement of work within 180 days. A floodplain development permit shall expire 180 days after issuance unless the permitted activity has been substantially begun and is thereafter pursued to completion.

(Ord. 31991-22A, passed 9-21-22; Ord. 32116-24, passed 10-9-24)