Fugitive particulate emissions.
Denver Revised Municipal Code § 4-25
in effectSec. 4-25. - Fugitive particulate emissions.
(a) No person shall allow or cause: (1) any materials to be handled, transported, or stored; (2) a building, including its appurtenances, or a construction haul road to be used, constructed, altered, repaired or demolished; or (3) any unenclosed activity, including demolition, excavation, backfilling, grading, clearing of land, construction or sandblasting without taking all reasonable measures as the department requires to prevent particulate matter from becoming airborne. All persons shall take reasonable measures to prevent the visible discharge of fugitive particulate emissions beyond the lot line of the property on which the emissions originate. The measures taken must be effective in the control of fugitive particulate emissions at all times on the site, including periods of inactivity such as evenings, weekends, and holidays as well as any other period of inactivity. Based upon the size of the construction site, proximity to sensitive receptors, or history of noncompliance with the provisions of this chapter, the department may require a fugitive particulate control plan for such activities.
(1) [Plan requirements.] The fugitive particulate control plan shall:
a. Be subject to department review, and if the department finds the plan to be inadequate, the department may require modifications;
b. Include the name and contact information of the person(s) responsible for the implementation of the plan and the person(s) responsible for the particulate generating activities;
c. Be effective in the control of fugitive particulates at all times, including evenings, weekends, and holidays, regardless of whether activities are being conducted at the site;
d. Identify each potentially fugitive particulate generating activity and operation to be carried out on the site and the actual and potential sources of fugitive emissions on-site;
e. Identify one (1) primary control measure and one (1) contingency control measure for each activity, operation or source of fugitive emissions identified above. A list of potential control measures may be obtained from the department;
f. Include at least daily vacuuming or wet sweeping of the right-of-way adjacent to individual projects to control any materials that are tracked out or that otherwise have come to be located in adjacent right-of-way; and
g. Be implemented for the duration of the project.
(2) Fees:
a. The board may require by rule and regulation payment of nonrefundable fees to be paid upon submittal of a fugitive dust control plan. The fees are to be of amount sufficient to offset all costs associated with the fugitive dust control plan review, including costs of administration and enforcement.
b. All fees must be paid at the time of filing the application for review with the department. No application will be valid or complete until all fees have been paid.
(Ord. No. 293-90, 5-29-90; Ord. No. 683-08, § 10, 12-8-08)
Source: City and County of Denver, Revised Municipal Code and Charter (Municode Library, library.municode.com)URL: https://library.municode.com/co/denver/codes/code_of_ordinances?nodeId=TITIIREMUCO_CH4AIPOCO_ARTIIISTSO_S4-25FUPAEMFetched: 10/27/2026