Sec. 43-104. - Required inspections.
The building official, upon notification, may make the inspections as set forth in this section.
Footing inspection: To be made after excavations for footings are complete and any required reinforcing steel and form work is in place. Setbacks from property lines, adequate soil conditions, and footing depth, width and location shall be verified.
Framing inspection: To be made after all framing, fire blocking, bracing and roof coverings are in place and all pipes, chimneys and vents are complete and the rough electrical, plumbing and heating inspections are approved. All structural elements shall be inspected, and the vertical reinforcing steel for foundations shall be verified.
Fire caulking: Fire caulking shall be inspected at the time of the framing inspection at penetrations within concealed spaces. All fire caulking shall be identified with the UL assembly number, applicator's name and product used. The method of identification will be a self-adhesive tag applied to the location.
Firewall: Firewalls in two-family dwellings must be completed and inspected at the time of the framing inspection. Firewall penetrations and top-of-wall conditions shall be inspected prior to the placement of any ceilings or other finishes.
Final inspection: To be made after the building and finish grading is completed and ready for occupancy.
Certificate of occupancy inspection: To be made prior to occupancy of any new structure or when the use of any structure changes. This inspection may be substituted for the final inspection. See also sections 43-111 and 43-112.
Special inspections: Special inspections shall be made as required in the International Building Code.
Ice and water shield inspection: It shall be the responsibility of the contractor to provide the inspector with photographic documentation that ice and water shield material has been installed on the project. The photograph must contain a street view of the home with the address clearly visible and identifying landmarks from that photograph on the roof. Failure to comply with this provision will require the roofing material to be removed at the contractor's expense so that an onsite inspection can be performed.
Other inspections: In addition to the inspections specified above, the building official may make or require other inspections of any construction work to ascertain compliance with the provisions of this code, the building code and other laws which are enforced by this jurisdiction.
(Ord. No. 33582, § 1(43-104), 6-27-95; Ord. No. 35988, § 14, 7-9-02; Ord. No. 41512, § 14, 7-10-18)