§ 25-4-40 - ACTION IN 15 DAYS AFTER APPLICANT RESPONSE.
(A) The requirements of this section are mandated by state law and supersede any contrary provisions of the City Code.
(B) In this section, applicant response means the information provided by the applicant to the director to address the conditions of approval or reasons for disapproval of an application for preliminary plan or plat.
(C) An applicant response:
(1) must adequately address each condition of approval or reason for the disapproval;
(2) must include only changes only as necessary to address the condition of approval or reason for disapproval; and
(3) may not include substantial changes unrelated to the condition of approval or reason for disapproval.
(D) Upon receipt of an applicant response to a preliminary plan or plat application that requires Land Use Commission consideration, the director shall:
(1) determine if the applicant response meets the requirements in Subsection (C), and
(2) schedule the application for consideration by the Land Use Commission not later than the 15th day after the applicant response was submitted.
(E) Upon receipt of an applicant response to a preliminary plan or plat the director shall:
(1) determine if the applicant response meets the requirements in Subsection (C), and
(2) approve, approve with conditions, or disapprove with reasons, the preliminary plan or plat not later than 15 days after the applicant response was submitted.
(F) If the applicant response as submitted complies with the provisions of Subsection (C), and the director fails to comply with the time limits for action in this section, the application for preliminary plan or plat is approved by operation of law.
Source: Ord. No. 20190822-117, Pt. 25, 9-1-19; Ord. No. 20230831-141, Pt. 24, 9-11-23.