Small project review requirement
Mont. Code Ann. § 75-2-505
in effect75-2-505. Small project review requirement
The department shall review a permit application within 5 working days of receipt of a complete application and an appropriate fee for an asbestos project that:
(1) involves more than 10 square feet but less than 160 square feet in surface area;
(2) involves more than 3 linear feet but less than 260 linear feet of pipe; or
(3) involves more than 3 cubic feet but less than 35 cubic feet of volume.
En. Sec. 2, Ch. 309, L. 2015.
Source: Montana Legislative Services Division (mca.legmt.gov)URL: https://mca.legmt.gov/bills/mca/title_0750/chapter_0020/part_0050/section_0050/0750-0020-0050-0050.htmlFetched: 10/20/2026