Contracts; changes authorized.
Neb. Rev. Stat. § 73-1117
in effect73-1117. Contracts; changes authorized.
A design-build contract and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit an authorized agency in agreement with the design-builder or construction manager to make changes in the project without invalidating the contract.
Laws 2025, LB660, § 17.
Source: Nebraska Legislature (nebraskalegislature.gov)URL: https://nebraskalegislature.gov/laws/statutes.php?statute=73-1117Fetched: 10/20/2026