What are the funding limitations on an individual TTF bridge project?
23 C.F.R. § 661.37
in effectThe following funding provisions apply in administration of the TTFBP:
(a) There are no funding limitations on an individual TTF bridge application, but the PE estimated cost will be based on the following fee scale:
Estimated Construction Cost:
Up to $1,000,000—Use up to 20% for PE
$1,000,000 to $5,000,000—Use up to 15%-20% for PE
$5,000,000 to $10,000,000—Use up to 10%-15% for PE
Over $10,000,000—Use up to 10% for PE
(b) Requests for additional funds for PE or construction may be submitted along with proper justification to FHWA for consideration. The request will be considered on a case-by-case basis. There is no guarantee for the approval of the request for additional funds.