Identification and shipping requirements.
41 C.F.R. § 101-27.206-2
in effectEffective Manufacturers shall, whenever practicable, be required to mark the unit or container with the month and year of manufacture or production and the batch number on all shelf-life items (60 months or less) procured from other than GSA sources. Whenever practical, the supplier shall be required to ship or deliver material within a given number of months from the date of manufacture or production. These “age on delivery” requirements should not be imposed in such a manner as to unduly restrict competition at any trade level. The following guidelines are suggested as appropriate for most shelf-life items:
Shelf-life period
Age on delivery
25 mos. or more6 mos.
19 to 24 mos4 mos.
13 to 18 mos3 mos.
7 to 12 mos2 mos.
6 mos. or less1 mo. or less.