§ 12-29 — Wiring installed without a permit
Code of Ordinances, City of Burlington, Vermont (Current through Ord. 8-3-26, passed August 3, 2026) · Burlington Code of Ordinances § 12-29
Corpus is an independent public-information project, not the official City of Burlington website. Stable reference: corpuslaw.us/code/7313a3b6-93ba-43ad-9948-57883c3c0a7b
12-29 Wiring installed without a permit.
Whenever any electrical work or wiring is found to have been installed without a permit where one is required, the electrical inspector is authorized to cut the wires, remove fuses, disconnect the switches or otherwise make the specific circuit or system inoperative until such a permit has been secured from the electrical inspector. The fee for the late permit shall be as set forth in section 12-26.
(Ord. of 10-27-03, eff. 11-26-03)