33.470.040 Regulations for Residential Uses
A.
Noise disclosure statement in the 55, 65, and 68 DNL. The regulations of this subsection
apply to sites in the 55, 65, and 68 DNL contours. Before a building permit is issued for new
residential construction or reconstruction where the total cost of improvements is 75
percent or more of the total assessed improvement value of the site, the owner must sign
the City's noise disclosure statement. The noise disclosure statement acknowledges that
the property is located within the 55, 65, or 68 DNL noise contour and signifies the owner's
awareness of the associated noise levels. The noise disclosure statement must be recorded
in the County records by the owner. A packet containing the noise disclosure statement is
available at the Development Services Center.
B.
Noise easement in the 65 and 68 DNL. The regulations of this subsection apply to sites in
the 65 and 68 DNL contours. Before a building permit is issued for new residential
construction or reconstruction where the total cost of improvements is 75 percent or more
of the total assessed improvement value of the site, the owner must dedicate a noise
easement to the Port of Portland. The easement authorizes aircraft noise impacts over the
grantor's property at levels established by the DNL noise contour. Any increase of the DNL
noise level above that stated on the easement will not void nor be protected by the
easement. The easement forms are available at the Development Services Center.
C.
Noise insulation required in 65 and 68 DNL. The regulations of this subsection apply to
sites in the 65 and 68 DNL contours. New dwelling units allowed by this chapter within the
65 and 68 DNL contours must be constructed with sound insulation or other means to
achieve a day/night average interior noise level of 45 dBA. Reconstructed dwelling units
where the total cost of improvements is 75 percent or more of the total assessed
improvement value of the site must also meet this standard. Garages and similar accessory
structures that do not include living area are not subject to this requirement.
1.
Certified by acoustical engineer. An engineer registered in Oregon who is licensed in
acoustical engineering must certify that the building plans comply with the
performance standard for sound insulation prior to the issuance of a building permit.
2.
City provides list. The City, in consultation with the Port of Portland, will provide a list
of at least three registered engineers licensed in acoustical engineering.
3.
Port of Portland pays for sound insulation certification. At an owner's request, the
Port of Portland is responsible for the costs of the noise insulation certification of
dwelling units submitted by an engineer on the City list. The Port of Portland will pay
for the cost of the certification required by this section, but not design, materials, or
labor costs associated with installing the sound insulation. The owner has the option
to retain any registered engineer licensed in acoustical engineering not on the list, at
the owner's expense.
D.
Residential use and density.
1.
Within the 68 DNL noise contour. Where any part of a site is within the 68 DNL noise
contour, it is subject to the following:
a.
New residential uses.
(1) New residential uses prohibited. New residential uses are prohibited within
the 68 DNL or higher noise contour except as allowed specifically by this
subsection. If a site is divided by a 68 DNL noise contour all dwelling units
must be located entirely outside the 68 DNL noise contour.
(2) Exemption. Sites that had a Farm and Forest, Limited Single Family, Low
Density Single Family, or Medium Density Single Family Comprehensive Plan
Map designation on January 1, 1981 or a County Residential Comprehensive
Plan designation or zoning on that date are exempt from this prohibition.
Dwelling units added to these sites must meet the requirements of this
chapter for residential development within the 65 DNL contour.
b.
Replacement housing.
(1) Existing housing within the 68 DNL noise contour may be replaced within 5
years if it is damaged or destroyed by fire or other causes beyond the
control of the owner. A houseboat that is intentionally removed from its slip
by the owner may be replaced within 5 years. A manufactured dwelling that
is intentionally removed from a manufactured dwelling park may be
replaced within 5 years.
(2) Natural disasters. The replacement time of 5 years is extended to 15 years
for manufactured dwelling parks if:
•
Manufactured dwelling units are damaged or destroyed by a natural
disaster such as a flood, earthquake, fire or other causes beyond the
control of the manufactured dwelling park owner; and
•
At least 30 percent of the manufactured dwelling units in the
manufactured dwelling park are either destroyed or significantly
damaged. A unit is significantly damaged if the repair cost is 75 percent
of the value of the unit.
2.
Within the 65 DNL noise contour. Where a site is within the 65 DNL noise contour, it is
subject to the following:
a.
Sites that have a residential Comprehensive Plan Map designation are prohibited
from developing to a residential density higher than that of the R10 zone.
b.
Except as provided in paragraph D.3, sites that have a commercial
Comprehensive Plan Map designation are prohibited from developing to a
residential density higher than that of the RM2 zone.
3.
In the Hayden Island plan district, residential density may be transferred as specified
in 33.532.240.
(Amended by: Ord. No. 164244, effective 7/1/91; Ord. No. 165376, effective 5/29/92; Ord. No.
174263, effective 4/15/00; Ord. No. 176469, effective 7/1/02; Ord. No. 178509, effective 7/16/04;
Ord. No. 182429, effective 1/16/09; Ord. No. 183124, effective 9/18/09; Ord. No. 184521, effective
5/13/11; Ord. No. 189805, effective 3/1/20.)
The City of Portland is committed to providing meaningful access. To request translation,
interpretation, modifications, accommodations, or other auxiliary aids or services, contact 311,
Relay: 711.
503-823-4000: Traducción e Interpretación | Biên Dịch và Thông Dịch | अनुवाद तथा व्याख्या
口笔译服务 | Устный и письменный перевод | Turjumaad iyo Fasiraad
Письмовий і усний переклад | Traducere și interpretariat | Chiaku me Awewen Kapas
www.portland.gov/bps/accommodation