26-158 Stormwater management plan.
(a) Review and approval. The department of public works will review each stormwater management plan to determine its conformance with the provisions of this division, unless such review is explicitly exempted within this division. Within thirty (30) days after receiving a complete plan and application, the department of public works shall in writing:
(1) Approve the plan;
(2) Approve the plan subject to such reasonable conditions as may be necessary to secure substantially the objectives of this division, and require that the issuance of the zoning permit and/or building permit be subject to these conditions; or
(3) Disapprove the plan, indicating the reason(s) and procedure for submitting a revised plan.
(b) Plan requirements. The stormwater management plan shall be prepared and signed by a licensed, professional engineer who shall verify and demonstrate conformance to the applicable water quality treatment standards and stormwater management design criteria contained in this division. The stormwater management plan shall contain both narrative and map(s) that clearly provide the following information:
(1) Contact information. The name, address, and telephone number of all persons having a legal interest in the property and the tax reference number and parcel number of the property or properties affected and similar information on the persons charged with the responsibility of constructing, maintaining and managing such stormwater systems.
(2) Site plan. A map indicating the location of existing and proposed buildings, roads, parking areas, utilities, structural stormwater management and sediment control facilities. The map will also clearly show proposed land use with tabulation of total lot size in acres, percentage of surface areas to be disturbed, percentage of existing and proposed impervious surfaces, drainage patters, locations of utilities, limits of clearing and grading, and all easements, including those easements necessary for required maintenance of all stormwater treatment practices.
(3) Base map. A one (1) inch = two hundred (200) feet topographic base map of the site which extends a minimum of three hundred (300) feet beyond the limits of the proposed development and indicates existing surface water drainage including streams, ponds, culverts, ditches, and wetlands, including associated buffer zones, and current land use including all existing buildings, utilities, roads, and significant natural and manmade features not otherwise shown.
(4) Calculations. Sufficient engineering analysis to show that the proposed stormwater treatment practices are capable of controlling runoff from the site in compliance with this division and the Vermont Stormwater Manual. The analysis shall also include hydrologic and hydraulic design calculations for the pre-development and post-development conditions for the design storms specified in the department of public works design manual with specific emphasis on demonstrating how post-development flows are maintained for discharges to the MS4 and/or where applicable demonstrating how post-development flows are detained for discharges to the CS.
(5) Soils report. A soils report that addresses the hydrologic properties of onsite soils shall be submitted. The soils report and accompanying information shall be based on the VSMM (latest edition) or the Underground Injection Control Rule, Chapter 11 (latest edition) which ever is applicable.
(6) Operation maintenance and repair plan. The design and planning of all stormwater management facilities shall include detailed operation maintenance and repair procedures to ensure their continued function. These plans will identify the parts or components of a stormwater management facility that needs to be maintained. The operation and maintenance and repair plan shall also include:
a. A landscape plan. The applicant must present a detailed plan for the management of vegetation at the site after construction is finished, including who will be responsible for the maintenance of vegetation at the site and what practices will be employed to ensure that adequate vegetation cover is preserved.
b. Maintenance easements. Prior to the issuance of any permit that has a stormwater management facility as a requirement, the applicant or owner of the site must execute a maintenance easement that shall be binding on all subsequent owners of land served by the stormwater management facility. The purpose of the maintenance easement shall be to allow access to the stormwater management facility to perform maintenance as required by the maintenance agreement noted in subsection c. below. The easement shall provide for access to the facility at reasonable times for periodic inspection by the city, or its contractor or agent, and for regular or special assessments of property owners to ensure that the facility is maintained in proper working condition to meet design standards and any other provisions established by this section. The property owner shall record such easement, in a form and format approved by the city attorney, in the city land records with the city clerk’s office.
c. Maintenance agreement. The applicant must execute a maintenance agreement binding on all subsequent owners of land served by an onsite stormwater management measure. The maintenance agreement shall be recorded in the land records before the issuance of a building permit and shall specify the required maintenance for all stormwater treatment practices, along with a maintenance schedule specifying when and how often maintenance is performed on the stormwater treatment practices and a demonstrated financial ability to perform such maintenance. Such agreement shall be in a form and format approved by the city attorney, and be filed in the city land records. The owner is responsible for maintenance of stormwater management facilities; however, the city may accept dedication of existing or future stormwater management facilities for public maintenance and inspection.
d. Maintenance inspections. All stormwater management facilities must be inspected by the department of public works no less than once annually to identify maintenance and repair needs and to ensure compliance with the requirements of this division. Any identified maintenance and/or repair needs found must be promptly addressed by the responsible party. The inspection and maintenance requirement may be increased as deemed necessary by the city to ensure proper functioning of the stormwater management facility.
e. Records of installation and maintenance activities. Parties responsible for the inspection, operation and maintenance of a stormwater management facility shall make records of the installation and of all maintenance and repairs and shall retain the records for at least five (5) years. These records shall be made available to the director upon request and/or as specifically outlined in the maintenance covenant.
f. Failure to maintain practices. If a responsible party fails or refuses to meet the requirements of the maintenance covenant, the city, after proper notice, may correct a violation of the design standards or maintenance needs by performing all necessary work to place the facility in proper working condition and/or shall handle the matter as a violation per section 26-4, penalties and enforcement.
(7) Landscaping and stabilization requirements. Any area of land for which the natural vegetative cover has been either partially or wholly cleared or removed by land disturbance activities subject to this division shall be revegetated within ten (10) business days from the substantial completion of such clearing and construction. Additionally, the following requirements apply until such time as final site stabilization has been achieved:
a. Reseeding must be done with an annual or perennial cover crop accompanied by placement of straw mulch or its equivalent of sufficient coverage to control erosion until such time as the cover crop is established over ninety (90) percent of the seeded area.
b. Replanting with native woody and herbaceous vegetation must be accompanied by placement of straw mulch or its equivalent of sufficient coverage to control erosion until the plantings are established and are capable of controlling erosion.
c. Any area of revegetation must exhibit survival of a minimum of seventy-five (75) percent of the cover crop throughout the year immediately following revegetation. Revegetation must be repeated in successive years until the minimum seventy-five (75) percent survival for one (1) year is achieved.
d. Any and all accumulated sediments transported offsite and deposited onto city streets, and sidewalks shall be routinely and frequently swept up to prevent their discharge into stormwater and/or the city’s public sewer.
(Ord. of 12-15-08(2), § 26-3-26)