For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 2.251 — Responsibility to Prevent Soil Erosion and Discharge of Sediments

Code of the City of Grand Rapids, Michigan (Supp. No. 70: codified through Ordinance No. 2026-08, enacted April 14, 2026) · Grand Rapids City Code § 2.251

Corpus is an independent public-information project, not the official City of Grand Rapids website. Stable reference: corpuslaw.us/code/75a73789-f49a-4a0c-807c-c5f9f738e212

Sec. 2.251. - Responsibility to Prevent Soil Erosion and Discharge of Sediments.

(1) It shall be the responsibility of the property owner and all other persons participating in, causing or being factually or legally responsible for any earth change to provide soil erosion and sedimentation control to adequately prevent soil from being eroded and discharged onto adjacent properties, or into a CSDS, a public street or right-of-way, wetland, creek, stream, water body or floodplain. (2) During any earth change that exposes soil to an increased risk of erosion, the property owner and any other person participating in such an earth change shall, at a minimum: (a) Prevent damage to or impairment of any wetland, creek, stream or water body on or near the site, (b) Prevent damage to any public utilities or services within the limits of grading and along any routes of travel of the equipment, (c) Prevent damage to adjacent property, (d) Determine, apply for and receive, all applicable approvals or permits prior to the commencement of work, (e) Implement the proposed work in accordance with the approved plans and in compliance with all the requirements of this Chapter and any permits issued pursuant to this Code, (f) Maintain all necessary or required soil erosion and sediment control measures including, but not limited to, measures required to comply with the provisions of this Chapter, (g) Prevent entry of soil, sediment, miscellaneous debris or other materials and promptly remove any material applied, dumped or otherwise deposited on any other properties, public streets, highways, sidewalks, or other public thoroughfares including catch basins, storm pipes, ditches, drainage swales, creeks or other bodies of water. Removal within twenty-four (24) hours shall be required, unless such materials present an immediate hazard to public health and safety or the environment. In which case immediate removal may be required, (h) Refrain from grading on land so close to the property line as to endanger any adjoining public street, sidewalk, alley or any public or private property without supporting and protecting such property or structures from settling, cracking or other damage which might result, (i) The owner shall have the soil erosion and sediment control measures inspected weekly and within twenty-four (24) hours of a rain event of sufficient quantity to cause runoff. The inspection for sites one (1) acre or greater shall be conducted by a EGLE certified Construction Site Stormwater Operator who shall maintain written inspection logs on forms approved by the City Manager.

(Ord. No. 2022-20, § 1, 7-26-22)

Ask a question about Grand Rapids law

Corpus searches the Grand Rapids sections it holds and shows the ones that match, with their citations. Free, no sign-in.