§ 74-518 — Performance and maintenance bonds

Atlanta City Code (Code of Ordinances, Part II) (Supp. No. 108, Update 1: codified through Ordinance No. 2026-37 (26-O-1511), enacted September 30, 2026) · Atlanta City Code § 74-518

Corpus is an independent public-information project, not the official City of Atlanta website. Stable reference: corpuslaw.us/code/7657d97b-0015-48f1-b754-74d554850cd9

Sec. 74-518. - Performance and maintenance bonds.

For development that requires an operation and maintenance agreement, the owner or applicant shall post a performance bond as required by section 74-509(c)(4), and in accordance with the following requirements: (1) The bond amount shall be $3,000.00 plus a prorated amount of $3,000.00 per disturbed acre for any amount or fraction greater than one acre or, where the permit application relates to a site that is subject to a stormwater master plan approved in accordance with section 74-525, the bond amount shall be calculated by reference to the estimated disturbed acres or fraction thereof for all of the parcels of land that are subject to the stormwater master plan; (2) The bond shall be issued by a bonding company licensed and registered in Georgia; (3) The bond shall ensure that the stormwater management system remains intact and functioning according to its design; (4) The term of the bond shall extend from the date that the bond is posted until three years from the date that the final inspection was completed pursuant to section 74-43(f) of the Code; and (5) The bond shall be written to the benefit of the city and shall obligate the bonding company to correct any violations of this article for the term of the bond. (6) The bond may be released when the city receives the first annual inspection and maintenance report under section 74-517(e) that certifies that the stormwater management system is compliant. (7) Failure to maintain or renew the bond, should it expire, shall be a violation of this article, and shall be a separate violation for each day of such failure. (8) If during the term of the bond and after written notice is provided by city to the relevant parties, the owner or applicant fails to bring the stormwater management system into compliance with this article, the owner or applicant shall be deemed in violation of this article. In addition to other fines or penalties, the owner or applicant shall be deemed to have forfeited the bond. Upon notice by the city that the bond is forfeited, the bonding company shall bring the stormwater management system into compliance. Alternatively, the city may undertake the necessary work to bring the stormwater management system into compliance and the bonding company shall be responsible for the associated costs up to the amount of the bond. Any additional amounts that may be outstanding will be recovered under section 74-520.

(Ord. No. 2020-66(20-O-1498), § 1, 11-25-20)