Sec. 11-133. - General conditions.
The following conditions shall be compiled with and agreed to by any person acting as such or as a contractor prior to drilling or constructing a well within the city, which conditions shall, in any event, apply to all wells drilled or constructed within the city:
(1) Wells shall have an outer casing of wrought iron or black steel pipe having a standard line pipe weight. Joints may be welded or made up with heavy threaded couplings.
(1) (a) Alternate casing material. Polyvinyl chloride (PVC) pipe may be used for well casing or liner pipe for drilled wells only. All casing material shall be new and shall conform to the manufacturing standard ASTM F480. Any PVC pipe used for well construction or repair shall, at a minimum, meet specifications for ASA schedule 40 and have a working pressure rating of not less than two hundred (200) p.s.i. at seventy-three (73) degrees F. Other nonmetallic pipe shall not be used. Joints shall be joined by solvent bonding, threaded couplings, or other method approved by the manufacturer.
(2) Drilled wells shall not be closer than one-half mile horizontally to an existing well furnishing water to the people of the city.
(3) The annular ring between the outside of the casing and the wall of the hole shall be scaled by forcing into it a neat portland cement grout, using the Halliburton Method or an approved equal, and weighing not less than fourteen and five-tenths (14.5) pounds per gallon. The annular ring shall not be less than one and one-half (1.5) inches in thickness.
(4) Tight joint between well casing and pump head: Pump head shall be connected to the outside casing by a watertight threaded connection or by the outside casing being carried to a point not less than one (1) inch above the pump head foundation. Before setting the pump head casing the contractor shall pour cement grout over the pump head foundation to provide a seal between the foundation and pump head casing to prevent water entering the well under the pump head casing when a partial vacuum is created.
(5) The casing shall extend from the top of the water bearing sand to a point at least one (1) inch above the top of the motor foundation.
(6) No drilling operation or other work in the well will be permitted within seventy-two (72) hours after the grouting of the casing, except that should quick-setting cement be used, this period may be reduced to twenty-four (24) hours.
(7) Provision for disinfection: Upon approaching the water-bearing stratum the contractor shall, from then on until the completion of the well-drilling operation, carry not less than five (5) parts per million of free chlorine in the drilling water and mud. Not less than one (1) part per million of free chlorine shall be maintained in the water used for development. In the case of gravel wall wells the contractor shall disinfect the gravel as it is being placed in the well with a water solution containing not less than five (5) parts per million of free chlorine.
(8) Upon completion of the well, it shall be disinfected with a chlorine solution of such strength and volume that at least fifty (50) parts per million will be obtained in all parts of the well. The solution shall remain in the well for at least four (4) hours.
(9) After development of the well, a minimum of two (2) consecutive chlorine-free water samples shall be examined by the state board of health for their approval, and upon approval being received by the city, such water supply may then be utilized.
(10) Pump head foundation: Pump head shall be mounted on a chamfered concrete foundation not smaller than twenty-four (24) inches square at the top, extending not less than eighteen (18) inches into solid ground and not less than eighteen (18) inches above the finished grade. If the pump head base is fitted with vacuum relief openings, these shall be protected by nipples and inverted ells, capped with fly screen.
(11) Provision for sampling directly from well: Contractor shall furnish and install on the pump discharge pipe near the pump head a three-quarter-inch hose bib in a horizontal position.
(12) Provision for filling test holes or abandoned well holes: Any test holes drilled shall be, when they have served their purpose, backfilled to the surface of the ground with clay mud carrying five (5) parts per million of free chlorine. If, for any reason, the contractor shall abandon any hole drilled for developing the well, he shall likewise backfill all such holes as provided herein for test holes. In each case the top twenty (20) feet of mud placed in any hole shall be thoroughly compacted.
(13) Determination of depth of well: The boring samples shall be obtained at intervals of ten (10) feet and shall be submitted to the state board of health for their findings.
(Code 1963, § 30-7; Ord. No. 2350, § 2, 4-8-03)