Facilitated partnering.
San José Municipal Code § 27.28.130
in effect27.28.130 - Facilitated partnering.
A. For Major Public Works Contracts in the amount of ten million dollars ($10,000,000) or more, an independent facilitator must conduct the pre-construction Partnering workshop required by Section 27.28.120.
B. For Major Public Works Contracts in the amount of one million dollars ($1,000,000) or more but less than ten million dollars ($10,000,000), the Contractor has the option, upon reasonable notice to the City, of having an independent facilitator conduct the pre-construction Partnering workshop required by Section 27.28.120.
(Ord. 30540.)
Source: City of San José, Municipal Code (Municode Library, library.municode.com)URL: https://library.municode.com/ca/san_jose/codes/code_of_ordinances?nodeId=TIT27PRPUWO_CH27.28DIRE_PT3PA_27.28.130FAPAFetched: 11/1/2026