Sec. 30-19. - Inspections.
(a)
The engineering division of the public works department is authorized to conduct an initial and a final inspection for each project permitted pursuant to section 30-10, as well as additional inspections as set forth in this section.
(b)
The city engineer may require additional inspections, to occur as often as once per week, if the right-of-way project requires a maintenance of traffic plan or if the project exceeds thirty (30) days.
(c)
The city engineer may require re-inspections of any right-of-way project for any of the following reasons:
(1)
Because permittee was not available at the site, did not have the permit on site in a visible and accessible location, or because permittee submitted an incorrect address;
(2)
Because permittee's work did not comply with applicable codes and had to be corrected;
(3)
Because permittee had not completed work prior to calling for an inspection;
(4)
Because permit or code violations were allegedly occurring at the site or because such violations had been discovered in a previous site visit or inspection.
(d)
Fees for inspections shall be as set forth in the right-of-way permit and inspection fees resolution. All planned inspection fees shall be paid in full prior to inspection approval being given. Re-inspection fees shall be paid before scheduling of the final inspection whenever required.
(Ord. No. 07-4724, § 3, 5-21-07; Ord. No. 13-5033, § 1, 1-7-13; Ord. No. 20-5325, § 1, 5-4-20)