Sec. 24-433. - Submission of work plans and coordination of work.

(a) Submission of owners' work plans. On the first City working day of each April and October, each owner shall submit to the Director, in a format prescribed by the Director, a plan detailing all work involving excavation that such owner anticipates performing or causing to be performed in any public rights-of-way during the three-year period immediately following such submission. An owner may add, change or delete any item of work in its three-year plan but shall notify the Director of such addition, change or deletion upon doing so. Any owner that does not propose work during the three-year period shall submit in lieu of the plan of work required by this section a statement in a form prescribed by the Director that no work is anticipated. Once he has filed such a statement, the owner shall immediately notify the Director of any planned work, along with other information on street condition and use, as soon as such work becomes reasonably foreseeable. (b) Composite list of owners' planned work. As soon as practicable following receipt and compilation of the owners' plans of work, the Director shall make available for review a composite list of all such work designated in the plans submitted. The Director shall cause the composite list to be maintained in a computerized database or similar computerized system to the maximum extent practicable. Owners shall keep themselves apprised of the current status of the composite list. Prior to issuing a permit, the Director shall check each application against the composite list and may require applicants to: (1) Coordinate their excavations with one another; (2) Coordinate excavations with ongoing or scheduled construction and maintenance work by the City; and (3) Complete excavations before the City begins construction and maintenance work. (c) Street construction plan. The Director shall prepare a three-year street construction plan showing all proposed reconstruction, repaving and resurfacing of the public rights-of-way for which it is responsible for maintaining. The Director shall revise and update this street construction plan on a semiannual basis within three months of the receipt date for three-year plans from owners. In order to facilitate coordination and minimize the cost of excavation, the Director shall make the street construction plan available for public inspection. (d) Notice of City work. At least 120 calendar days prior to undertaking the repaving or reconstruction of any block, the Director shall send a written notice by first class mail of the proposed repaving and reconstruction to each owner with facilities in that block. (e) Waiver of requirements. The Director may, for good cause shown, waive in writing the coordination requirements of Subsection (b) of this section. The Director shall consider the following criteria before granting a waiver and shall document his consideration of these criteria in writing: (1) The effect of the owner's proposed excavations on the movement of traffic in the surrounding area; (2) The owner's need for the facility; (3) The need to facilitate the deployment of new technology; and (4) The public health and safety.

(Code 2004, § 90-461; Code 2015, § 24-433; Code 2020, § 24-433; Ord. No. 2005-113-55, § 1, 4-25-2005)