Sec. 2-537. - Minimum standards.
Except as otherwise provided in this subdivision, a responsible contractor shall appear to meet the following qualifications:
(1) Have adequate financial resources, or ability to obtain such resources as required during performance of the contract;
(2) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing business commitments, commercial as well as governmental;
(3) Have a satisfactory record of timely performance of city contracts. Contractors who are seriously deficient in current contract performance, when the number of contracts and the extent of deficiency of each are considered, shall, in the absence of evidence to the contrary or circumstances properly beyond the control of the contractor, be presumed to be unable to meet this requirement. Past unsatisfactory performance due to failure to apply necessary tenacity, or perseverance to do an acceptable job, shall be sufficient to justify a finding of nonresponsibility;
(4) Have a satisfactory record of integrity. The following provisions, while not exclusive, shall be sufficient to justify a finding of nonresponsibility:
a. Failure to pay taxes and fees due and owing the city;
b. A conviction of the contractor or a principal officer thereof for commission of a criminal offense, as incident to obtaining or attempting to obtain a public contract or in the performance of such contract;
c. A conviction, of the contractor or principal officer thereof, under state or federal statutes, for embezzlement, theft, forgery, bribery, falsification or destruction of records, receiving stolen property, or any other offense indicating a lack of business integrity or business honesty which currently, seriously and directly affects responsibility as a city contractor;
(5) Have a satisfactory record of performance of contractual provisions. Violation of contract provisions of a character which justify a finding of nonresponsibility include:
a. Deliberate failure without good cause to perform in accordance with the specifications provided in the contract;
b. A recent record of failure to perform or of unsatisfactory performance in accordance with the terms of one or more contracts;
c. In particular, failure to comply with prevailing wage and related federal, state, and city requirements;
provided, however, that failure to perform or unsatisfactory performance caused by acts beyond the control of the contractor shall not be considered to be a basis for a finding of nonresponsibility;
(6) Have the necessary technical skills or ability to obtain them;
(7) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
(8) Have a satisfactory record of having provided in any bid submitted to the city the evidence of good faith efforts to achieve disadvantaged business enterprise participation in the contract through subcontracting as required by the procurement and records division as a condition for a bid to be deemed responsive, in accordance with the provisions of chapter 35, article IV, division of this Code. To that end, and in accordance with this subdivision, the failure to have a satisfactory record of having provided such bids and such evidence of good faith efforts shall subject such contractor to the penalties provided in section 2-539.
(Code 1968, § 20-49(b); Ord. No. 92-016, § 1, 3-19-92; Ord. No. 92-053(sub 1), § 1(c), 7-2-92)