§ 22.3403 — Procurement Agreements

San Diego Municipal Code (City Clerk PDFs, pages revised through October 2026) · San Diego Municipal Code § 22.3403

Corpus is an independent public-information project, not the official City of San Diego website. Stable reference: corpuslaw.us/code/7a35bb30-bdee-4085-88a7-47553cf86886

§22.3403 Procurement Agreements

(a) In order to facilitate the negotiation, letting and administration of Qualifying Design-Build Contracts, the City Manager, with the approval of the Council, may enter into Procurement Agreements with Procurement Consultants. Procurement Agreements are Consultant agreements as otherwise set forth in the Charter or Municipal Code. Each Procurement Agreement shall obligate the Procurement Consultant to: (1) administer the negotiation, letting, and performance of the Qualifying Design-Build Contracts pursuant to the procedures and terms established in the Procurement Agreement, which procedures shall be consistent with the requirements of Division 34; (2) determine the scope of the design and construction services to be provided by the Design-Build Entity; and (3) perform the services described in Section 22.3403(a)(1) and (2) in a manner which shall cause the Qualifying Complex Public Facility to be completed: (A) such that the general program and design concepts for the facility established by the Council are incorporated into the Qualifying Complex Public Facility, provided that the City may permit the Procurement Consultant, in administering the design and construction of the Qualifying Complex Public Facility, to revise the general program and design concepts so long as the revisions do not materially detract from the anticipated experience to be obtained in the use of the facility; and (B) such that the total expenditure of City funds is less than or equal to the maximum amount established by the Council for design and construction of the facility. (4) endeavor in good faith to cause the completion of the facility within the general timeline for completion of the facility established by the Council, as the general timeline may be extended due to events of force majeure or other circumstances not reasonably within the control of the Procurement Consultant. (b) The Procurement Agreement may include other provisions consistent with Division 34, including provisions to the effect that: (1) the Procurement Consultant may be authorized to administer the Qualifying Design-Build Contract; (2) the Procurement Consultant may be authorized to undertake any of the activities described in Sections 22.3404, 22.3405, 22.3406, 22.3409 or 22.3410 on behalf of the City, including, without limitation, administrating the preparation of the request for proposal, the prequalification of Design-Build Entities, the selection of the Design-Build Entity, the competitive negotiation of the Qualifying Design-Build Contract, and the letting of the Qualifying Design-Build Contract, all on behalf of the City as the City’s authorized agent for such purpose; (3) the Procurement Consultant, without additional approval from the City, may be permitted to enter into agreements related to the design and construction of the Qualifying Complex Public Facility so long as the Procurement Consultant enters into the agreements in its own name and without liability to the City; (4) the Procurement Consultant, without additional approval from the City, may be authorized to enter into other agreements for the provision of other goods and services ancillary to the Qualifying Complex Public Facility or the Qualifying Design-Build Contract so long as the Procurement Consultant enters into the agreements in its own name and without liability to the City; and (5) the City may pay directly or reimburse the Procurement Consultant for the costs incurred with respect to agreements described in Section 22.3403(b)(3) or (4) in addition to other provisions for the compensation of the Procurement Consultant. No payment or reimbursement shall be required or authorized if such payment or reimbursement would cause the total expenditure by the City to exceed the maximum amount approved by the Council for the design and construction of the Qualifying Complex Public Facility. (c) The agreements referenced in Section 22.3403(b)(3) and (4) may include, for example and without limitation, agreements with contractors, consultants or experts for the design, inspection and testing of portions of the Qualifying Complex Public Facility and agreements for the procurement of fixtures, furnishings and equipment to be provided to the Qualifying Complex Public Facility. (“Procurement Agreements” added 10-18-1999 by O-18696 N.S.)

Ask a question about San Diego law

Corpus searches the San Diego sections it holds and shows the ones that match, with their citations. Free, no sign-in.