in effectSec. 30-1030.4. - Procedures.
(a) Pre-submittal conference.
(1) Prior to submittal of a site plan application, an applicant may request, in writing, that the Director hold a pre-submittal conference to discuss the scope, features, and impacts of a proposed development and applicable regulations, policies, and procedures. As part of such request, an applicant shall submit a complete pre-application package, to include all drawings, data, and related materials described in procedures published by the Director for one of the following types of review, as specified by the applicant:
a. Conceptual review. Review of the general feasibility of the proposed development based on the physical characteristics of the land, its designated future land use in the master plan, its existing or proposed zoning designation, and the availability and capacity of transportation networks and utility infrastructure; or
b. Preliminary review. Preliminary compliance review of proposed development, as shown by an accurate site plan, in consideration of applicable, duly adopted laws, regulations, and policies.
(2) The Director shall have ten days from receipt of a complete pre-application request to determine the date of the pre-application conference, which shall occur as soon as reasonably possible given the complexity of the proposed development. Required pre-application conference attendees shall include the Director, or their designee, and the applicant, or the applicant's authorized representative.
(3) The Director shall promptly distribute a submitted and complete pre-application request to the directors of all affected city departments, who shall in turn assign qualified staff to examine the request and provide comments to the Director at least three days prior to the date of the pre-application conference.
(4) Within ten days following the date of a pre-application conference, the Director shall provide the applicant an advisory letter that discusses, but makes no formal determination about, one or more of the following:
a. Potential or likely deficiencies among the pre-application package materials, or markings of such deficiencies on those materials, and the laws, regulations or policies with which the deficiencies do not comply;
b. Discretionary modifications or corrections to the development described in the pre-application package that, though not required, would in the opinion of the Director promote health, safety, morals, comfort, prosperity, and general welfare in accordance with the spirit and intent of identified sections of City Code; and
c. Other permits and approvals the applicant may need to secure prior to, or in conjunction with, construction of the development described in the pre-application package materials.
(b) Submittal.
(1) An applicant shall submit a site plan application for review and approval in accordance with procedures published by the Director.
(2) Within ten days from receipt of a site plan application, the Director shall notify the applicant whether the site plan application is complete. A complete site plan application is one for which both of the following apply:
a. The site plan application is submitted in accordance with this subsection (b), including, without limitation, the payment of all applicable fees; and
b. The site plan application includes, per procedures published by the Director or as the Director otherwise requests, all drawings and data needed for evaluation of the site plan in accordance with the scope of review described in Section 30-1030.2(b).
(3) If the Director determines a site plan application is complete, the Director shall notify the applicant that the site plan has been officially submitted for approval, effective as of the date applicant submitted such complete application.
(c) State review.
(1) Within ten days from the time a site plan is officially submitted, the Director shall determine whether any feature of such site plan requires approval from any State agency or public authority authorized by state law.
(2) If any feature of an officially submitted site plan requires approval from any State agency or public authority authorized by State law, the Director shall notify the applicant of such requirement and forward such site plan to each applicable State agency and public authority for review. The Director may proceed with City review described in Subsection (d) of this section during such time, but shall not complete such review before receipt of all approvals from all applicable State agencies and public authorities.
(3) If no feature of an officially submitted site plan requires approval from any State agency or public authority authorized by State law, the Director shall proceed with City review.
(d) City review.
(1) The Director shall distribute an officially submitted site plan to the directors of all affected City departments, as determined by the Director. The Director and the directors of all other affected City departments shall assign one or more qualified staff to thoroughly review the site plan in accordance with the scope of review described in Section 30-1030.2(b) and in good faith identify all site plan deficiencies, if any.
(2) Within 30 days following receipt of an officially submitted site plan from the Director, the director of each affected City department shall provide the following to the Director:
a. A written list of specific deficiencies of a site plan, or markings of specific deficiencies on the site plan itself;
b. The laws, regulations or policies with which the deficiencies do not comply; and
c. Modifications or corrections needed for compliance.
(3) Within 30 days from receipt of a site plan from the Director, the director of each affected City department may provide the Director, in writing, a separate list of discretionary modifications or corrections to a site plan that, while not required, would in the opinion of such Director promote health, safety, morals, comfort, prosperity, and general welfare.
(4) The Director shall develop their own written list as described in Subsection (d)(2) of this section, may develop their own written list as described in Subsection (d)(3) of this section, and shall consolidate such lists with those received from the directors of all other affected City departments into a single document of site plan comments, which document shall distinguish site plan modifications and corrections necessary for site plan approval from discretionary site plan modifications and corrections.
(e) Decision.
(1) The Director shall render a decision to approve or disapprove an officially submitted site plan in the form of a written notice to the applicant within one of the following timeframes:
a. 60 days from the date an original site plan was first officially submitted; or
b. 45 days from the date a modified and corrected site plan that was previously disapproved was officially resubmitted; or
c. 35 days from the date all applicable State agencies and public authorities authorized by State law have provided the Director their written responses for a site plan that requires such responses.
(2) The Director shall approve a site plan if the Director concludes both of the following apply:
a. The site plan complies with the duly adopted statutes, ordinances, regulations, and policies described in Section 30-1030.2(b), as affirmed by the director of each affected City department; and
b. The site plan has received all needed state agency and public authority approvals.
(3) Notwithstanding the above, the Director may, by provision for variation in or exception from the general regulations of Chapter 25, approve an officially submitted site plan that does not strictly comply with Chapter 25 in the event either of the following apply:
a. The Director reasonably concludes from evidence presented by applicant that strict application of the regulations of Chapter 25 actually prohibit or unreasonably restrict the use of the property due to exceptional topographic conditions or other extraordinary or exceptional circumstances or conditions;
b. The Director is satisfied, upon presentation of evidence by applicant, that strict adherence to one or more regulations of Chapter 25 would result in substantial injustice or hardship.
(4) The Director shall disapprove a site plan if the Director concludes either of the following apply:
a. The site plan fails to comply with all applicable duly adopted statutes, ordinances, regulations, and policies described in Section 30-1030.2(b);
b. The site plan has not received all needed state agency and public authority approvals.
(5) In the event of disapproval, the Director shall provide the applicant with the following in addition to the written notice of disapproval:
a. A written list of specific deficiencies of a site plan or markings of specific deficiencies on the site plan itself;
b. The laws, regulations, or policies with which the deficiencies do not comply; and
c. To the greatest extent practicable, modifications or corrections that would permit site plan approval.
(6) Notwithstanding the approval or deemed approval of any submitted or resubmitted site plan, any deficiency in any proposed site plan that if left uncorrected would violate local, State or Federal law, regulations, mandatory Virginia Department of Transportation engineering and safety requirements, and other mandatory engineering and safety requirements, shall not be considered, treated or deemed as having been approved by the Director.
(f) Review of resubmittals.
(1) For a site plan that does not solely involve lots of commercial or residential real estate, the Director shall act on any proposed site plan the Director has previously disapproved within 45 days after such site plan has been modified, corrected, and resubmitted for approval.
(2) For a site plan that solely involves lots of commercial or residential real estate, the Director shall act on any proposed site plan the Director has previously disapproved within 45 days after such site plan has been modified, corrected, and resubmitted for approval, and the following shall apply to Director review of such resubmittal:
a. For purposes of this subsection (f)(2), the term "commercial" means all real property used for commercial or industrial uses, and the term "residential" means all real property used for single-family or multifamily use.
b. The Director shall only consider the following:
i. Deficiencies the Director identified in review of the initial site plan submittal that remain uncorrected; and
ii. Deficiencies that result from corrections made to address deficiencies identified in the initially submitted, previously disapproved site plan.
c. The Director shall provide the following to the applicant:
i. A written list of specific deficiencies of a site plan or markings of specific deficiencies on the site plan itself;
ii. The laws, regulations, or policies with which the deficiencies do not comply; and
iii. To the greatest extent practicable, modifications or corrections that would permit site plan approval.
d. The Director may provide the applicant a written list of specific deficiencies not identified in the review of the initial site plan or the resubmittal of a site plan that are considered a risk to health or safety.
e. In the event the Director disapproves not only an initially submitted site plan but also a resubmittal of such site plan, Director review of a second resubmittal of the site plan shall be limited solely to the previously identified deficiencies that caused its disapproval.
f. Notwithstanding the above, if any resubmitted a site plan includes a material revision of either infrastructure or physical improvements from an earlier submittal, or if a material revision in a resubmitted site plan creates a new required review by the Virginia Department of Transportation or by a State agency or public authority authorized by State law, then the Director's resubmittal review may consider not only deficiencies previously identified in the prior submittals but also deficiencies initially appearing in the resubmittal because of such material revision.
g. Subject to Subsection (e)(6) of this section, failure of the Director to approve or disapprove a resubmitted site plan within the time period required by this Subsection (f)(2) of this section shall cause such resubmitted site plan to be deemed approved.
(g) Withdrawal.
(1) An applicant may request, in writing, to withdraw a site plan from the review process at any time.
(2) If an applicant fails to submit modifications or corrections to remedy an incomplete site plan application or to correct identified deficiencies of an officially submitted, disapproved site plan application within in 180 days after the date of an incomplete or disapproved application notice from the Director, the Director shall notify the applicant that the application shall be withdrawn from consideration within 30 days from the date of such notice, which period the Director may extend as they deem reasonable under the circumstances if the applicant so requests.
(3) The Director shall not refund fees to the applicant for a site plan that has been officially submitted for 30 or more days.
(Code 2004, § 114-1030.4; Code 2015, § 30-1030.4; Code 2020, § 30-1030.4; Ord. No. 2004-180-167, §§ 3, 5, 6-28-2004; Ord. No. 2009-221-2010-9, § 1, 1-25-2010; Ord. No. 2023-101, § 5, 4-24-2023; Ord. No. 2024-314, § 3(30-1030.4), 12-9-2024)