Provision of subcontracting data.
Atlanta City Code § 2-1296
in effectSec. 2-1296. - Provision of subcontracting data.
(a) Any actual offeror awarded a contract under section 2-1188, section 2-1188.1, section 21189, section 2-1191, section 2-1191.1, or section 2-1192 on or after January 1, 2010 shall be required to submit, on an annual basis, information on its use of all subcontractors on all contracts held by the actual offeror to the office of contract compliance as follows, on a form prescribed by the chief procurement officer. This form shall be due to the chief procurement officer at the time of final execution of the awarded contract and, thereafter, by March 31 of each following calendar years, containing such information for the prior calendar year. However, no information shall be required to be provided under this section prior to March 31, 2011. Such information shall include, but shall not be limited to:
(1) The actual offeror's name, address, phone number, federal tax identification number, a primary contact, City of Atlanta contract names or numbers awarded to the actual offeror, and City of Atlanta contract amounts awarded to the actual offeror;
(2) All subcontracts with a value exceeding $1,000.00 entered into or maintained by the actual offeror on all contracts within the state of Georgia within the past year; and
(3) With respect to each such subcontract, the subcontractor's name, address, contact person, phone number, type of work, the approximate total value of the subcontract, the approximate amount paid to the subcontractor to date, and whether the subcontract was pursuant to a public project or a private project.
(b) Any actual offeror that submits a bid or proposal in response to a solicitation under section 2-1188, section 2-1188.1, section 2-1189, section 2-1191, section 2-1191.1, or section 2-1192 is encouraged to submit, along with its bid or proposal documents, the information described in subsection (a). An actual offeror that submitted such information in compliance with subsection (a) on or before the previous March 31 should not submit this information along with its bid or proposal documents.
(c) Penalties for noncompliance. An actual offeror who fails to comply with subsection (a), and whose failure to comply continues for a period of 60 calendar days after the contractor receives written notice of such noncompliance from the chief procurement officer, shall be subject to any or all of the following penalties:
(1) Withholding of ten percent of all future payments on all contracts actual offeror has with the city until the chief procurement officer determines that the contractor is in compliance with this section.
(2) Refusal of all future contracts or subcontracts with the city for a minimum of one year and a maximum of five years from the date upon which this penalty is imposed pursuant to the provisions contained in division 16 herein.
(d) Waiver of penalties. The chief procurement officer shall have the authority, in his or her sole discretion, to waive for good cause the requirements of subsection (a) or any penalties set forth in subsection (d).
(Ord. No. 2009-78(09-O-1876), § 7, 12-15-09)
Source: City of Atlanta, Code of Ordinances (Charter and Related Laws, General Ordinances, Land Development Code) (Municode Library, library.municode.com)URL: https://library.municode.com/ga/atlanta/codes/code_of_ordinances?nodeId=PTIICOORENOR_CH2AD_ARTXPRREESCO_DIV7COCLTHAD_S2-1296PRSUDAFetched: 10/28/2026