§129.0508 Initial Utilization of a Demolition/Removal Permit
A Demolition/Removal Permit shall become void if the work authorized and required by the permit has not begun within 60 calendar days of the date of permit issuance and has not been validated by an inspection.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.) (Renumbered from Section 129.0510 and amended 1-18-2018 by O-20897 N.S.; effective 2-17-2018. Former Section 129.0508 “Surety Required Prior to Demolition” repealed.)