Certificate of completion.
El Paso City Code § 18.02.111.7
in effect18.02.111.7 - Certificate of completion.
After the building official inspects the work completed under permit for a building, structure, electrical, fire protection, plumbing, mechanical, fuel gas, or similar system or structure that cannot be occupied, and finds no violations of the provisions of this Code or the technical codes, the building official is authorized to issue a certificate of completion. Such certificate of completion certifies that the work performed under the permit has been satisfactorily completed. The certificate of completion does not authorize the occupancy of any incomplete shell, building or structure.
(Ord. No. 019528, § 1, 8-1-2023)