7.5.102: GENERAL INFORMATION:
Table 7.5.1-A identifies the development procedures authorized by this UDC and establishes whether public notice is required, whether pre-submittal activities are required, the role of City review and decision-making bodies, and whether public hearings are required during each process.
Table 7.5.1-A R = Recommendation D = Decision A = AppealSummary of Review Procedures [1] M = Manager's Discretion (based on UDC Criteria and Standards) * = Quasi-judicial Public Hearing T = Suggested N = Published (Newspaper) Notice Required L = Mailed (Letter) Notice Required S = Posted (Sign) Notice Required
| Pre-Submittal Activities | Notice | Review and Decision-Making Bodies |
Procedure | Pre-Application Meeting | Neighborhood Meeting | Type Required | Staff/Manager | Historic Pres. Board | Planning Comm./FBZ Review Board | City Council | Code Ref.
Table 7.5.1-A R = Recommendation D = Decision A = AppealSummary of Review Procedures [1] M = Manager's Discretion (based on UDC Criteria and Standards) * = Quasi-judicial Public Hearing T = Suggested N = Published (Newspaper) Notice Required L = Mailed (Letter) Notice Required S = Posted (Sign) Notice Required
| Pre-Submittal Activities | Notice | Review and Decision-Making Bodies |
Procedure | Pre-Application Meeting | Neighborhood Meeting | Type Required | Staff/Manager | Historic Pres. Board | Planning Comm./FBZ Review Board | City Council | Code Ref.
Permits
Adult Use Permit | | | | D | | A [2] | A [2] | 7.5.502
Building Permits | T | | S [11] | D | R [11] | | | 7.3.304 .E [11]
Coordinated Sign Plan | | | | D | | A [2] | A [2] | 7.5.504
Front Yard Carport Permit | | | L | D | | A | A | 7.5.505
Grading and Erosion Control Permit | | | | D [3] | | | | 7.5.506
Home Occupation Permit | | | | D | | A [2] | A [2] | 7.5.507
Sign Permit | | | | D | | | | 7.5.508
Site Plan to Unplatted Lands | | | | D | | A | A | 7.5.509
Short Term Rental Permit | | | | D | | A [2] | A [2] | 7.5.510
Temporary Use Permit | | | | D | | A [2] | A [2] | 7.5.511
WCF Eligible Facilities Request | | | | D | | | | 7.5.512
WCF Permit | | | | D | | A | A | 7.5.513
Land Use and Development Plans
Land Use Plan | | | | D | | D*[6]/A | A | 7.5.514
With Annexation | T | M | N, L, S | R | | R | D |
With Rezoning | T | M | L, S | R | | R* | D* |
Development Plan | T | M | S[7] | D | | D* [8]/A | | 7.5.515
Amendments | T | M | L, S | D | | D*/A | |
Hillside Site and Grading Plan | T | | | D | | A | A |
Site Plan to Unplatted Land | T | | | D | | A | A | 7.5.509
Subdivision-Related Procedures
Amendment to Plat Restriction | T | | L, S | D | | A | A | 7.5.518
Final Plat, Plat Modification Prior to Recording, and/or Replat | | | | D | | | | 7.5.519
Preservation Area Boundary Adjustment | T | | L, S | D | | A | A | 7.5.520
Property Boundary/Lot Line Adjustment | T | | | D | | | | 7.5.521
Vacation Plat (no public streets or ROW) | | | | D | | | A | 7.5.522
Waiver of Replat | T | | | D | | | | 7.5.523
Variances and Adjustments
Administrative Adjustment | T | M | | D | | A | A | 7.5.524
Development Standards Adjustment | T | M | L, S | R | | D* | A | 7.5.525
Non-Use Variance | T | M | L, S | R | | D* | A | 7.5.526
Use Variance | T | M | L, S | R | | R* | D* | 7.5.527
Other Procedure
Historic Resources Alteration or Demolition | T | M | L, S | D [for Minor] | D* [for Major] /A | | A | 7.5.528
Interpretation of UDC | | | | D | | | | 7.5.529
Numeric Address Change | | | | See Section RBC312.7 of Regional Building Code | 7.5.530 | | |
Street Name Change | T | | N, L, S | | | D | A | 7.5.531
Decisions Requiring a Planning Commission Hearing
Conditional Use Permit | T | M | L, S | R | | D* | A | 7.5.601
Policy Decisions by City Council
Annexation of Land | T | M | N, L, S | R | | R | D | 7.5.701
Amendment to the UDC Text | | M | N | R | R[7] | R* | D* | 7.5.702
Vacation of Public Streets or Right of Way | T | M | N, L, S | R | | | D | 7.5.703
Zoning Map Amendment (Rezoning) | T | M | N, L, S | | R[7] | R* | D* | 7.5.704
Zoning Map Amendment (upon Annexation) | T | M | N, S | | | R | D | 7.5.704
Appeals
Appeals of Administrative Decisions [9] | | | L | | | A* | A | 7.5.415
Appeal of Planning Commission, FBZ Board, or Historic Preservation Board Decisions [10] | | | L, S | | D* | D* | A* | 7.5.705
NOTES: [1] The Manager may refer any item to the Planning Commission, FBZ Review Board, or Historic Preservation Board if found necessary for final review authority.[2] In the event of a denial, the Administrative Decision may be appealed to the Planning Commission.[3] Decision is made by the Stormwater Enterprise Manager; appeal is available to the Public Works Director.[4] Posting for ten (10) days after submitted and prior to final decision by Manager. [5] Decision is made by the Stormwater Enterprise Manager; appeal is available to the Drainage Board.[6] The Planning Commission will have the final approval only if the Manager refers an administrative level Land Use Plan for review.[7] If the application relates to an HP-O District[8] The Planning Commission will have the final approval only if the Manager refers an administrative level Development Plan for Review[9] Applicable to appealable Administrative Decisions as indicated in Table 7.5-1A[10] Applicable to appealable Planning Commission, FBZ Review Board, and Historic Preservation Board decisions as indicated in Table 7.5.1.[11] Requirements applicable only to applications for Accessory Dwelling Units as indicated in Section 7.3.304 .E.