Construction permit for parking facilities.
Omaha Municipal Code § 55-743
in effectSec. 55-743. - Construction permit for parking facilities.
(a) Required. Prior to the start of construction of any off-street parking facility, the property owner must obtain an off-street parking permit from the permits and inspections division of the planning department. The building official shall issue a certificate of occupancy, in accordance with chapter 43 of this Code, within 12 months after completion of construction, if the completed facility complies with the approved plan, as provided by this section.
(b) Plan review and approval; appeals.
(1) Prior to issuance of an off-street parking permit for a parking facility of ten or more stalls, a plan must be approved by the directors of the planning and public works departments, or their designees.
(2) Application for a permit shall include the following plans and specifications prepared by a registered architect, landscape architect or engineer, demonstrating compliance with the off-street parking and loading regulations. These plans and specifications shall include, but not be limited to:
a. The location of parking stalls, lighting, drive aisles, circulation ways and access points to the facility.
b. A landscape plan, indicating location, size and species of proposed landscaping.
c. A grading plan, showing existing and proposed grades at two-foot intervals.
d. The location and direction of drainage for stormwater runoff.
e. Indication of all structures or uses to be served by the facility.
f. Construction details necessary to demonstrate compliance with this chapter.
(3) Plans shall be reviewed for compliance with the standards and policies of this article and any other applicable ordinance or regulation.
(4) Permits shall be issued by the building official following approval of plans and specifications and in accord with those plans.
(5) Denial of an application for a permit to build an off-street parking facility may be appealed to the zoning board of appeals.
(c) Performance bond for installation of landscaping.
(1) If, at the time of an application for a certificate of occupancy, any required landscaping has not been installed, the developer or owner of a site must make fiscal arrangements (by bond, certificate of deposit, or letter or credit) satisfactory to the city in the amount of $2.00 per square foot of required landscaping not in place.
(2) The developer or owner shall grant the city permission to enter upon the land to install required landscaping if this has not been done within 12 months of the effective date of the certificate of occupancy.
(3) The city shall release any bond or other arrangement immediately when the permits and inspections division verifies that required landscaping has been installed.
(Code 1980, § 55-743; Ord. No. 42341, § 9, 10-27-20)
Source: City of Omaha, Municipal Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/ne/omaha/codes/code_of_ordinances?nodeId=OMMUCOCHGEORVOII_CH55ZO_ARTXIVOREPALORE_S55-743COPEPAFAFetched: 10/28/2026