§ 46-107 — Modification, suspension or cancellation of a permit

Atlanta City Code (Code of Ordinances, Part II) (Supp. No. 108, Update 1: codified through Ordinance No. 2026-37 (26-O-1511), enacted September 30, 2026) · Atlanta City Code § 46-107

Corpus is an independent public-information project, not the official City of Atlanta website. Stable reference: corpuslaw.us/code/85796a6b-3dce-48e8-838c-98d63997c4be

Sec. 46-107. - Modification, suspension or cancellation of a permit.

(1) After receiving a permit, the producer may request a material modification of the permit at any time by submitting to the CAOE a change request and change fee as set forth in code section 46-110. The CAOE's ability to process the change request shall be determined pursuant to the provisions established for processing applications, as set forth in subsections 46-106(2) and (3) above. The director's decision of whether to grant or deny the modification request shall be determined as set forth in subsections 46-106(4) through 46-106(14). Submission of a change request will not impact the validity of the permit already issued, except upon written request of the producer. (2) Where a producer has obtained a permit and abides by the material requirements thereof, the permit shall prevent the city's stoppage of activities that are authorized by the permit, except as otherwise set forth in subsection 46-107(3) below or as a result of applicable law. (3) In the event that the Atlanta Police Department, Atlanta Fire Rescue Department and/or other department of purview identifies a substantial public health or safety risk arising from or caused by the filming, and the producer is in material compliance with the permit, the following shall occur: (a) Where the substantial risk is identified prior to the commencement of the filming, the director and applicable department of purview shall employ reasonable efforts to consult with the producer and identify permit changes that are mutually acceptable to the producer and the city, and that remedy the health/safety issue(s). Where such efforts are unsuccessful, the director shall modify the permit in a manner that minimizes disruption of the filming as determined at the director's reasonable discretion, and that eliminates the substantial risk as reasonably determined by the department of purview. (b) Where the substantial risk is not imminent and is identified after the commencement of the filming, the director and applicable department of purview shall employ reasonable efforts to consult with the producer and identify permit changes that are mutually acceptable to the producer and the city, and that remedy the health/safety issue(s). Where such efforts are unsuccessful, the director shall modify the permit in a manner that minimizes disruption of the filming as determined at the director's reasonable discretion, and that eliminates the substantial risk as reasonably determined by the department of purview. (c) Where the substantial risk is imminent as reasonably determined by the department of purview and is identified after the commencement of filming, said department may place a stop work order on the filming if it finds that the order will likely alleviate the substantial risk. The stop work order may be issued without advance notice where the department of purview deems that a delay of the order will jeopardize public health and safety, and shall be lifted as quickly as possible after the risk is eliminated. The department of purview shall notify the director of the stop work order within two hours of its issuance. The director and applicable department of purview shall employ reasonable efforts to consult with the producer and identify permit changes that are mutually acceptable to the producer and the city, that will minimize the length and impact of the stop work order as decided by the producer, and that remedy the health/safety issue(s) as determined by the department of purview. (d) Changes made to the permit pursuant to this subsection 46-107(3) shall not require payment of a change fee. (4) Where the director, or a department of purview in consultation with the director, determines that the producer is violating material term(s) of the permit, the director shall decide the appropriate remedial actions after consulting with the department of purview and the producer. If the director and/or department of purview finds that a substantial public health or safety risk is arising from or caused by the material violation, the department of purview in consultation with the director may place an immediate stop work order on the filming without prior notice to the producer, and consultation with the producer shall occur after the work stoppage. The consultation between the director, department of purview and producer shall evaluate the nature and severity of the violation, whether the violation was intentional, whether permit modifications should be made, whether the stop work order should be lifted (where applicable), and what other actions should be taken (if any). Where the violation creates a substantial public health and/or safety risk, the remedial actions decided by the director will not be deemed final until the department of purview reviews the remedial actions and confirms that they will eliminate the health and safety risks.

(Ord. No. 2013-33(13-O-0641), § 3, 7-3-13)

Ask a question about Atlanta law

Corpus searches the Atlanta sections it holds and shows the ones that match, with their citations. Free, no sign-in.