in effectSec. 12-20. - Reporting—Capital projects.
(a) The Chief Administrative Officer shall cause the preparation of a written quarterly financial report that identifies the actual costs and any projected funding surplus or additional funding requirement for each capital project to provide the Council with a more accurate basis for the appropriation of funds for such projects and the submission of such report to the Council no later than 45 days after the end of each quarter. At a minimum, each report shall include the following for each capital project:
(1) The original cost estimate.
(2) The current cost estimate.
(3) The current appropriation.
(4) The funding source or sources.
(5) The year-to-date expenditures.
(6) The life-to-date expenditures.
(7) The amount of any additional funding requirement.
(8) Any balance remaining to the credit of any completed project.
(9) The amount of any balance remaining to the credit of a completed project that the Mayor transfers to an incomplete project pursuant to Section 6.19 of the Charter, including the title of each project to receive such reallocated funds and a brief explanation of the need for the additional funds for each such project.
(b) At the same time that the Mayor transfers any portion of the balance remaining to the credit of a completed project to an incomplete project pursuant to Section 6.19 of the Charter, the Chief Administrative Officer shall notify each member of the City Council and the Council Chief of Staff in writing of the transfer together with the information required by Subsection (a)(9) of this section.
(Code 2015, § 12-15.3; Code 2020, § 12-20; Ord. No. 2018-197, § 1, 7-23-2018)