§ 12.10.27 — Warranty Period Following Acceptance

Code of Ordinances, City of Tupelo, Mississippi (Supp. No. 15: codified through Ordinance of March 5, 2024 and Ordinance of June 4, 2024) · Tupelo Development Code § 12.10.27

Corpus is an independent public-information project, not the official City of Tupelo website. Stable reference: corpuslaw.us/code/871b02f5-2994-48c4-8125-47df754f1619

12.10.27. - Warranty Period Following Acceptance.

(1) If the Director of Development Services determines that the installed improvements meet all applicable city standards and all other conditions and requirements specified in the Development Agreement have been met and final construction plans are approved, then a Certificate of Initial Acceptance shall be issued, and the plat shall be recorded according to the procedures in Section 12.10.28 of this Code. (2) A one year warranty period begins with the first working day of the calendar year after the Certificate of initial acceptance is issued. During this warranty period any deficiencies in accepted improvements that are documented by the City Engineer or other city departments shall be the responsibility of the developer or subdivider to correct or repair. (3) The City shall not be obligated to maintain any improvements until one year without defects has passed and a Certificate of Final Acceptance shall be issued by the Director of Development Services. Failure to make required repairs within three months of the date on which the developer or subdivider is notified of the deficiency shall result in the revocation of any building permits issued to the developer or subdivider, and in the suspension of further issuance of additional building permits for construction on lots within the subdivision owned by the developer or subdivider. (4) The city may perform the necessary repairs, drawing upon the security provided under the development agreement, and if necessary, may also make every effort to collect payment from the subdivider or developer by all legal means including the placement of liens on lots owned by the subdivider or developer.

Ask a question about Tupelo law

Corpus searches the Tupelo sections it holds and shows the ones that match, with their citations. Free, no sign-in.