25.08.655 - Major public project construction variance
A. The Administrator may grant a major public project construction variance to provide relief from the exterior sound level limits established by this Chapter 25.08 during the construction periods of major public projects. A major public project construction variance shall provide relief from the exterior sound level limits during the construction or reconstruction of a major public project only to the extent the applicant demonstrates that compliance with the levels would: 1. Be unreasonable in light of public or worker safety or cause the applicant to violate other applicable regulations, including but not limited to regulations that reduce impacts on transportation infrastructure or natural resources; or 2. Render the project economically or functionally unreasonable due to factors such as the financial cost of compliance or the impact of complying for the duration of the construction or reconstruction of the major public project. B. A major public project construction variance shall set forth the period or periods during which the variance is effective, which period or periods shall be the minimum reasonably necessary in light of the standard set forth in subsection 25.08.655.A, and the exterior sound level limits that will be in effect during the period of the variance. Different major public project construction variances may be issued for distinct phases of a construction project, or one major public project construction variance may be issued for the entire major public project. The period or periods during which a major public project construction variance is effective may be stated in terms of calendar dates or in terms of the duration of a construction project or a phase or phases of a construction project. C. The Administrator shall condition a major public project construction variance as necessary to provide reasonable control or mitigation of the construction noise that may be expected to occur pursuant to the variance. D. One-year review and decision 1. No later than one year after the start of construction to which a major public project construction variance applies, the Administrator shall review, and provide opportunity for public comment on, the operation of the variance during the first year, including the provisions of the Noise Management and Mitigation Plan, and the conditions of the variance. For purposes of determining the date of the start of the project's construction work, site exploration work is excluded. 2. After considering the public comments received, the Administrator may modify the terms and conditions of the variance or the Noise Management and Mitigation Plan as needed, or revoke the variance, if the Administrator determines that the current variance, the conditions of the variance, or the Noise Management and Mitigation Plan are not adequately protecting the public health and safety or reasonably controlling or mitigating the construction noise, or that there are more reasonable methods of doing so. 3. The Administrator shall make a decision whether to modify or revoke a variance pursuant to this review within one year and 90 days after the start of construction work as provided in subsection 25.08.655.D.1. 4. Appeal. Any person aggrieved by the decision of the Administrator whether to modify a variance pursuant to this subsection 25.08.655.D may appeal such decision by filing an appeal in writing with the Hearing Examiner by 5 p.m. of the tenth day following the date of the issuance of the decision. A one-year review and decision for a Noise Management and Mitigation Plan for a light rail transit facility is not administratively appealable to the Hearing Examiner. When the last day of the appeal period is a Saturday, Sunday, or federal or City holiday, the appeal may be filed until 5 p.m. on the next business day. The Hearing Examiner appeal shall be conducted pursuant to Section 25.08.610. 5. Effective date. The decision of the Administrator whether to modify a variance pursuant to this subsection 25.08.655.D is effective 30 days following the decision unless it is appealed to the Hearing Examiner. If the Administrator's decision is appealed to the Hearing Examiner, the Administrator's decision does not take effect and the original terms and conditions of the variance remain in effect until the effective date of the Hearing Examiner decision. The Hearing Examiner decision is a final decision of the City for purposes of chapter 36.70C RCW, and is effective 30 days from the date of the decision, unless otherwise ordered by a court. If a court stays the effective date of the decision, the original unmodified variance shall remain in effect during the stay.
(Ord. 127228, § 38, 2025; Ord. 124843, § 82, 2015; Ord. 122923, § 43, 2009)
Ask a question about Seattle law
Corpus searches the Seattle sections it holds and shows the ones that match, with their citations. Free, no sign-in.