Sec. 328.110. - Repairs; Corrective Action Report.
Based on the recommendations in the Phase One report, any repairs determined to be required by the inspector must be permitted within six months and the repairs must be completed within 18 months. The permit application shall include a direct reference to the Phase One Inspection Report and the page and item or paragraph number of the repair being permitted. A copy of the Inspection Report page marking the noted repair item shall be submitted with the permit application. Based on the recommendations in the Phase Two report, all required repairs must be permitted in 90 days and completed within one year. The permit application shall include a direct reference to the Phase Two Inspection Report including the page and item or paragraph number of the repair being permitted. A copy of the Inspection Report page marking the noted repair item shall be submitted with the permit application. Following the completion of any repairs from either the Phase One or Phase Two Inspection Report, the Inspector and Association shall sign a Completion of Corrective Action Report to the Building Inspection Division through the Division's permitting system.
(Ord. 2022-842-E, § 3; Ord. 2025-30-E, § 14)
Ask a question about Jacksonville law
Corpus searches the Jacksonville sections it holds and shows the ones that match, with their citations. Free, no sign-in.